Construction paymentdates calculator.
The deadlines, set out Late payment interest calculator Guides to payment, notices and time
- Interim Valuation DateThe due date is 12 days after it, under the form as publishedTuesday 17 November 2026
- Payer's last day for its Payment NoticeFrom the payer, not later than 5 days after the due date. If none arrives by the end of this day, the payee may give its own notice in default from the next dayNo bank holiday falls in this period.Friday 4 December 20268 days left
- Pay Less Notice deadlineThe last day to give a Pay Less Notice, 5 days before the final dateEvery day counts, bank holidays included.Tuesday 8 December 202612 days left
- Final date for payment14 days after the due date. The notified sum, or the sum in a valid Pay Less Notice, must be paid by thenNo bank holiday falls in this period.Sunday 13 December 202617 days left
This calculator applies the Construction Act and the Scheme for Construction Contracts to the dates you enter, for construction contracts under the law of England and Wales. It does not read your contract, so the result is right only if your contract says nothing different, and it is not for a contract with a residential occupier. This is general information, not legal advice. Check the result against your contract before you rely on it.
Published periods for the JCT Design and Build Sub-Contract 2016 (DBSub/C), counted as the Construction Act requires in England and Wales. Scotland and Northern Ireland have their own rules, not modelled here. Your contract may change them: we check yours when you start.