Plain answers to the questions Main Contractors and Sub-Contractors ask about payment, notices and time, under JCT and NEC contracts, bespoke contracts and the Construction Act.
Payment
- How to answer a Sub-Contractor's applicationA Main Contractor answers a Sub-Contractor's application with a Payment Notice within 5 days of the due date, and a Pay Less Notice if it will pay less.
- When is retention released?Under JCT half the retention is released at practical completion and the rest after making good. Sub-contracts and NEC4 Option X16 set their own release points.
- How is the final date for payment worked out?The contract sets it. If not, the Scheme makes it 17 days after the due date, leaving out Christmas Day, Good Friday and bank holidays.
- How to work out the due date for paymentThe due date is when a payment becomes due. Your contract sets it; if not, the Scheme makes it the later of 7 days after the period ends or the claim.
- What happens if no Payment Notice is given?If no Payment Notice is given in time, the payee's own notice or application can become the notified sum, payable unless a Pay Less Notice follows.
- What is a Pay Less Notice and what must it say?A Pay Less Notice tells the payee you will pay less than the notified sum. It must state the sum and how it is worked out, and be given in time.
Time
- Liquidated damages under JCT and NECUnder JCT the Employer needs a Non-Completion Certificate and notices to deduct liquidated damages. NEC4 Option X7 sets delay damages at a daily rate.
- How to give notice of delay under a JCT contractUnder JCT clause 2.27, give notice forthwith once delay becomes reasonably apparent, with the cause, any Relevant Event and an estimate of the delay.
- What goes in a JCT extension of time applicationA JCT extension of time claim needs the Relevant Event, its effect on completion, an estimate of delay and updates, under clauses 2.27 to 2.29.
Late payment
- Can I suspend work for non-payment?Yes. If the notified sum is not paid by the final date, you can suspend after at least seven days' notice stating the grounds, under section 112.
- Late payment interest in construction contractsInterest is usually due. Without a substantial contract remedy, the Late Payment Act adds 8% over Bank Rate plus £40 to £100 compensation.
NEC contracts
- How is an NEC compensation event assessed?Under NEC4 the Contractor quotes for a compensation event within three weeks, showing Defined Cost, Fee and delay. The Project Manager replies within two weeks.
- How to notify a compensation event under NEC4Under NEC4 clause 61.3, notify a compensation event within eight weeks of becoming aware of it, or the Prices and Completion Date may not change.
- When must an NEC early warning be given?Under NEC4 clause 15.1, give an early warning as soon as you become aware of a matter that could raise the Prices, delay Completion or a Key Date.
Variations
- How are variations valued under JCT?Under JCT a variation is valued at the contract rates for similar work, with a fair allowance for changed conditions, or at fair rates if it is not similar.
- How to confirm a verbal instructionA verbal instruction under JCT has no immediate effect. Confirm it in writing within 7 days. Under NEC4 an instruction must be in a form that can be recorded.
Contract terms
- Checking a construction contract before you signBefore signing a construction contract, check the payment dates, notice periods and time bars, retention, delay damages and how notices must be served.
- What are back-to-back sub-contract terms?Back-to-back terms pass main contract obligations down to a Sub-Contractor. JCT staggers the periods so the Main Contractor can pass claims up in time.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.