How to claim loss and expense under JCT

Under JCT clause 4.21, notify loss and expense as soon as it is apparent, send an initial assessment and update it monthly. The Employer's side ascertains it.

Published
20 November 2026
For
Main Contractors and Sub-Contractors
Law checked
20 November 2026
Reading time
5 minutes
On this page
  1. The entitlement
  2. The Relevant Matters
  3. Giving notice
  4. The assessment and the updates
  5. The ascertainment
  6. Sub-Contractors under a JCT sub-contract
  7. Under NEC4
  8. A worked example
  9. Common questions

Under a JCT Standard Building Contract, the Contractor is entitled to direct loss and/or expense caused by a Relevant Matter that materially affects regular progress of the works, or by deferment of possession. To recover it, the Contractor must notify the Architect/Contract Administrator as soon as the likely effect becomes reasonably apparent, send an initial assessment with supporting information, and update it monthly. The Architect/Contract Administrator or Quantity Surveyor then ascertains the amount, and it is added to the Contract Sum.

This article describes the JCT Standard Building Contract 2016 and the JCT Design and Build Sub-Contract 2016 for Sub-Contractors. If your contract is on a later edition or is amended, check the clause numbers and periods in your own copy.

The entitlement

Clause 4.20.1 gives the Contractor reimbursement of direct loss and/or expense it incurs, or is likely to incur, because regular progress of the works has been or is likely to be materially affected by a Relevant Matter, or because possession of the site was deferred under clause 2.5. The entitlement is subject to the Contractor complying with clause 4.21.

Clause 4.20.2 adds that there is no entitlement where the conditions provide that there is to be no addition to the Contract Sum, or to the extent the Contractor is reimbursed under another provision. So a cost already paid through the valuation of a Variation cannot be claimed again.

The Relevant Matters

The Relevant Matters are listed in clause 4.22. In summary they are Variations (other than those where loss and expense was agreed in an accepted quotation), certain instructions of the Architect/Contract Administrator such as postponement, opening up work that proves to be in accordance with the contract, and dealing with discrepancies, and any impediment, prevention or default by the Employer, the Architect/Contract Administrator, the Quantity Surveyor or any Employer's Person.

The list is narrower than the list of Relevant Events for an extension of time. Exceptionally adverse weather, for example, can justify more time but is not a Relevant Matter, so it does not bring money with it.

Giving notice

Clause 4.21.1 requires the Contractor to notify the Architect/Contract Administrator as soon as the likely effect of a Relevant Matter on regular progress becomes, or should have become, reasonably apparent. The words "or should have become" matter. The test is when the effect should reasonably have been apparent, not when the Contractor actually noticed it.

The notice and the delay notice under clause 2.27 often go together, because the same event usually causes both. They are separate obligations, so make sure each is covered.

The assessment and the updates

Under clause 4.21.2 the notification is accompanied, or followed as soon as reasonably practicable, by the Contractor's initial assessment of the loss and/or expense incurred and any further amounts likely to be incurred, with the information reasonably necessary to ascertain it.

Clause 4.21.3 then requires the Contractor to update that assessment and information at monthly intervals until everything needed to ascertain the total has been supplied, in the form and manner the Architect/Contract Administrator reasonably requires.

The information is what decides the claim. Keep records of the extra time on site, the people and plant affected, the periods of disruption and the costs actually incurred, and link each one to the Relevant Matter that caused it.

The ascertainment

Clause 4.21.4 sets the Employer's side a timetable. The Architect/Contract Administrator or Quantity Surveyor notifies the Contractor of the ascertained amount within 28 days of receiving the initial assessment and information, and within 14 days of each update. Each ascertainment is made by reference to the information the Contractor supplied, in enough detail for the Contractor to see where it differs from the Contractor's own assessment.

Amounts ascertained are added to the Contract Sum under clause 4.23, so they flow into the interim certificates. Anything notified but not yet ascertained is dealt with in the final adjustment under clause 4.25. Clause 4.24 keeps the Contractor's other rights and remedies.

Sub-Contractors under a JCT sub-contract

The JCT Design and Build Sub-Contract 2016 follows the same pattern in clauses 4.14 to 4.17. The Sub-Contractor notifies the Contractor as soon as the likely effect of a Relevant Sub-Contract Matter on regular progress becomes, or should have become, reasonably apparent, sends an initial assessment and updates it monthly.

The Contractor's periods are longer. It notifies its ascertainment within 42 days of receiving the initial assessment and information, and within 28 days of each update. That leaves the Main Contractor time to pass the claim up under the main contract where the cause lies with the Employer.

Under NEC4

NEC4 has no separate loss and expense claim. Cost is dealt with through compensation events. Under clause 63.1 the change to the Prices is assessed as the effect of the compensation event on the actual Defined Cost of the work done by the dividing date, the forecast Defined Cost of the work not done by the dividing date and the resulting Fee. The Contractor's quotation for the compensation event covers time and money together.

A worked example

Invented example

Initial assessment received
Mon 15 Mar 2027
Ascertainment due
Wed 14 Apr 2027
Update received
Thu 15 Apr 2027
Next ascertainment due
Thu 29 Apr 2027

On a Standard Building Contract 2016, late structural information from the design team holds up the frame. The Contractor notifies the Architect/Contract Administrator under clause 4.21.1 as soon as the effect on progress is apparent, and its initial assessment and supporting information are received on Monday 15 March 2027.

The 28 day period begins the next day. Good Friday on 26 March 2027 and Easter Monday on 29 March 2027 are Public Holidays, which clause 1.5 leaves out, so the ascertainment is due by Wednesday 14 April 2027 rather than Monday 12 April 2027. The Contractor's first monthly update is received on Thursday 15 April 2027, and the next ascertainment is due within 14 days, by Thursday 29 April 2027.

Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.

Questions

Common questions

Is loss and expense the same as an extension of time?
No. An extension of time moves the Completion Date. Loss and expense is money for the effect on regular progress. The same event can give rise to both, but each has its own notice and its own test, and one does not follow automatically from the other.
How long does the Employer's side have to ascertain loss and expense?
Under clause 4.21.4 of the Standard Building Contract 2016, the Architect/Contract Administrator or Quantity Surveyor notifies the ascertained amount within 28 days of receiving the initial assessment and information, and within 14 days of each update.
Is there loss and expense under NEC4?
Not as a separate claim. Under NEC4 the effect of a compensation event on cost is assessed as part of the change to the Prices, using Defined Cost and the resulting Fee (clause 63.1).

Preparing the claim

Puncheur's loss and expense page explains what the application contains and how it follows on from the notice of delay and the extension of time.

See the Loss and expense application

Sources

  1. JCT Standard Building Contract Without Quantities 2016, clauses 1.5 and 4.20 to 4.25. jctltd.co.uk. Checked 20 November 2026.
  2. JCT Design and Build Sub-Contract Conditions 2016, clauses 4.14 to 4.18. jctltd.co.uk. Checked 20 November 2026.
  3. NEC4 Engineering and Construction Contract, June 2017 with amendments October 2020, clauses 60.1 and 63.1. neccontract.com. Checked 20 November 2026.

A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.