How to give notice of delay under a JCT contract
Under JCT clause 2.27, give notice forthwith once delay becomes reasonably apparent, with the cause, any Relevant Event and an estimate of the delay.
On this page
Under a JCT Standard Building Contract, the Contractor must give notice of delay "forthwith" once it becomes reasonably apparent that the progress of the works is being or is likely to be delayed. The notice goes to the Architect/Contract Administrator. It sets out the material circumstances, including the cause of the delay, and names any event the Contractor considers a Relevant Event. Particulars of the expected effects, with an estimate of the delay, follow as soon as possible if they cannot go in the notice itself.
This article describes the JCT Standard Building Contract 2016 and 2024 editions and the JCT Design and Build Sub-Contract 2016. Amended and bespoke versions are common, so read the clause in your own contract.
When the duty arises
Clause 2.27.1 of the 2016 Standard Building Contract applies "if and whenever it becomes reasonably apparent" that progress of the works, or a section, is being or is likely to be delayed. Two points follow from that wording.
The trigger is an expected delay, not a proven one. A hold up on site that is likely to affect progress is enough, even before anyone knows how long it will last.
The duty also applies whatever the cause. The notice must describe the delay and its cause, and then identify any event that, in the Contractor's opinion, is a Relevant Event. A delay that turns out to be the Contractor's own responsibility is still a delay to progress.
What the notice must contain
Clause 2.27.1 asks for the material circumstances, including the cause or causes of the delay, and the identity of any Relevant Event. The Relevant Events are listed in clause 2.29. They include Variations, certain instructions from the Architect/Contract Administrator, deferment of possession of the site, impediment or prevention by the Employer or its people, work by statutory undertakers, exceptionally adverse weather, loss or damage by a Specified Peril, strikes and force majeure.
Clause 2.27.2 then requires particulars of the expected effects of each event, including an estimate of any expected delay to completion beyond the Completion Date. Those particulars go in the notice if practicable, or otherwise in writing as soon as possible afterwards.
Clause 2.27.3 requires the Contractor to notify any material change in the estimated delay or the other particulars. Under the 2016 edition it must also supply further information the Architect/Contract Administrator reasonably requires. Under the 2024 edition, requests for further information are made under clause 2.27.4. A notice of delay is the start of a process, not a single letter.
What the Architect/Contract Administrator must do
Under the 2016 edition, clause 2.28.2 requires the Architect/Contract Administrator to notify its decision as soon as reasonably practicable and in any event within 12 weeks of receiving the required particulars, whether or not an extension is given. Where less than 12 weeks remain before the Completion Date, it must try to decide before that date.
The 2024 edition shortens this. Clause 2.28.2 of the 2024 Standard Building Contract sets 8 weeks, and clause 2.27.4 lets the Architect/Contract Administrator ask for further information not later than 14 days after receiving the particulars or a notification of change. Check which edition your contract uses before relying on either period.
The decision must state the extension attributed to each Relevant Event (clause 2.28.3). After the Completion Date has passed, clause 2.28.5 allows a further review, and the 2016 edition requires a decision not later than 12 weeks after practical completion.
Sub-Contractors on a JCT sub-contract
The JCT sub-contracts follow the same pattern. Under the Design and Build Sub-Contract 2016, clause 2.17.1 requires the Sub-Contractor to give notice forthwith to the Contractor once it becomes reasonably apparent that the commencement, progress or completion of the sub-contract works is being or is likely to be delayed. The wording asks for the cause or causes "insofar as the Sub-Contractor is able", which recognises that a Sub-Contractor may not know the full cause.
Under clause 2.18.2 of that sub-contract, the Contractor must notify its decision within 16 weeks of receiving the required particulars. For a Main Contractor, the sub-contract notice often feeds its own notice under the main contract, so passing it on quickly protects both positions.
A worked example
Invented example
- Particulars received
- Wed 2 Jun 2027
- Information request deadline
- Wed 16 Jun 2027
- 2024 edition decision, if no request
- Wed 28 Jul 2027
- 2016 edition decision
- Wed 25 Aug 2027
On a Standard Building Contract, the Contractor's site manager reports on Tuesday 1 June 2027 that the structural engineer's revised details for the third floor have not arrived. That is likely to delay the frame. The Contractor gives notice the same day, naming the late information as an impediment by the Employer's design team under clause 2.29.6.
The Contractor sends its particulars and an estimate of five weeks' delay on Wednesday 2 June 2027, by email, received that day. Under the 2024 edition, the Architect/Contract Administrator may ask for further information by Wednesday 16 June 2027, and must decide within 8 weeks, by Wednesday 28 July 2027 if it asks for no further information. Under the 2016 edition, the decision is due within 12 weeks, by Wednesday 25 August 2027. No Public Holiday falls in any of those periods.
JCT clause 1.5 leaves Public Holidays out of periods stated in days. Periods stated in weeks, like the 8 and 12 weeks for a decision, run as calendar weeks.
Getting the notice right
The Contractor should give notice forthwith and keep the cause, the effect and the estimate in separate parts, so each can be updated. It should name the Relevant Event and the sub-clause of 2.29 it relies on, and serve the notice in the way clause 1.7 and the contract particulars allow. A notice that arrives weeks after site knew of the problem invites an argument about whether it was given forthwith.
Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.
Questions
Common questions
- How soon must I give notice of delay under JCT?
- Clause 2.27.1 of the JCT Standard Building Contract says forthwith, once it becomes reasonably apparent that progress is being or is likely to be delayed. Do not wait for the delay to happen or to be measured.
- Do I need to know the length of the delay before I give notice?
- No. The notice states the material circumstances and the cause. The particulars and the estimate of delay can follow in writing as soon as possible afterwards under clause 2.27.2.
- How long does the Architect/Contract Administrator have to decide?
- Under the 2016 edition, within 12 weeks of receiving the required particulars. Under the 2024 edition, within 8 weeks.
Drafting the notice
Puncheur's notice of delay page explains what the document contains and how it is drafted from your own JCT or bespoke contract.
See the Notice of delay / extension of time noticeSources
- JCT Standard Building Contract Without Quantities 2016, clauses 1.5, 2.27, 2.28, 2.29. jctltd.co.uk. Checked 19 November 2026.
- JCT Standard Building Contract With Quantities 2024, clauses 2.27.4 and 2.28.2. jctltd.co.uk. Checked 19 November 2026.
- JCT Design and Build Sub-Contract Conditions 2016, clauses 2.17 and 2.18. jctltd.co.uk. Checked 19 November 2026.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.