Guides · NEC contracts
When must an NEC early warning be given?
Under NEC4 clause 15.1, give an early warning as soon as you become aware of a matter that could raise the Prices, delay Completion or a Key Date.
On this page
Under the NEC4 Engineering and Construction Contract, the Contractor and the Project Manager must each give an early warning as soon as they become aware of any matter that could increase the total of the Prices, delay Completion or a Key Date, or impair the performance of the works in use. The warning is given by notifying the other. If the Contractor fails to give a warning that an experienced contractor could have given, it can lose part of the value of a later compensation event.
This article describes the NEC4 Engineering and Construction Contract, June 2017 edition with amendments October 2020. Subcontracts and amended versions may differ, so check your own clause.
What the early warning is for
Clause 15 is about dealing with problems while they can still be avoided or reduced. A matter goes on the Early Warning Register, and the Project Manager and Contractor meet to decide what to do about it.
It applies to both sides. The Project Manager has the same duty to warn as the Contractor, which is easy to forget when the warning would come from the side of the Client (NEC4's name for the party paying for the works).
When to give it
The trigger in clause 15.1 is awareness. As soon as either party becomes aware of a matter that could have one of the listed effects, it notifies the other. The matter does not need to have happened, and its effect does not need to be certain. "Could" is the test.
Either may also give an early warning of any other matter that could increase the Contractor's total cost. Early warning is not needed for a matter for which a compensation event has already been notified.
How to give it
An early warning is a notification. Under clause 13.7, a notification the contract requires is communicated separately from other communications. A mention in meeting minutes or a progress report is not a safe substitute. Use the communication system the Scope sets out, and make the subject clear.
Say what the matter is, what it could affect, and what you suggest is done about it. The point of the process is a decision on action, so a warning that comes with a proposal is more useful.
The register and the meetings
Clause 15.2 requires the Project Manager to issue a first Early Warning Register within one week of the starting date, and to instruct the Contractor to attend a first early warning meeting within two weeks of the starting date. Later meetings are held at least as often as the interval stated in the Contract Data, until Completion of the whole of the works, and whenever either party instructs the other to attend.
At the meeting those attending consider proposals to avoid or reduce the effect of each matter, decide on the actions to be taken and who will take them, and decide which matters can be removed from the register. The Project Manager issues the revised register within one week of the meeting. If a decision needs a change to the Scope, the Project Manager instructs it at the same time.
A Subcontractor attends an early warning meeting if its attendance would help decide the actions to be taken.
What happens if no warning is given
If the Project Manager decides that the Contractor did not give an early warning of an event that an experienced contractor could have given, it says so in its instruction to submit quotations for the compensation event (clause 61.5).
The compensation event is then assessed as if the Contractor had given the early warning (clause 63.7). In practice, that can reduce the change to the Prices and the Completion Date to what it would have been if the problem had been raised and acted on in time.
So a late or missing early warning does not stop a compensation event, but it can cost money and time.
A worked example
Invented example
- Starting date
- Mon 4 Jan 2027
- First register due
- Mon 11 Jan 2027
- First meeting by
- Mon 18 Jan 2027
- Early warning given
- Wed 3 Feb 2027
The starting date on an NEC4 contract is Monday 4 January 2027. The Project Manager must issue the first Early Warning Register by Monday 11 January 2027, and the first early warning meeting should take place within two weeks, by Monday 18 January 2027.
On Wednesday 3 February 2027 the Contractor's survey shows that a buried service is not where the drawings show it. Diverting it could delay a Key Date for handing over the access road. The Contractor notifies an early warning that day, as a separate communication, and proposes a trial hole and a meeting with the utility. The matter goes on the register, and the next meeting decides on the trial hole and who will arrange it.
Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.
Questions
Common questions
- Who gives an early warning under NEC4?
- Both the Contractor and the Project Manager. Clause 15.1 requires each to notify the other as soon as either becomes aware of a matter that could increase the total of the Prices, delay Completion or a Key Date, or impair the performance of the works in use.
- What happens if the Contractor does not give an early warning?
- If the Project Manager decides an experienced contractor could have given one, it says so when instructing quotations, and the compensation event is assessed as if the warning had been given.
- Do I need an early warning for a compensation event I have already notified?
- No. Clause 15.1 says early warning of a matter for which a compensation event has already been notified is not required.
Preparing the warning
Puncheur's NEC early warning page explains what the notification contains and how it is set out from your contract.
See the NEC early warning noticeSources
- NEC4 Engineering and Construction Contract, June 2017 with amendments October 2020, clauses 13.7, 15, 61.5 and 63.7. neccontract.com. Checked 19 November 2026.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.
See also the terms of use.