NEC compensation event notification and quotation
An NEC4 compensation event notification with the eight-week time bar checked for you, and a quotation build-up of Defined Cost, risk allowances and the Fee with the delay to Completion and Key Dates, with live formulas.
- When it is due
- Within eight weeks of becoming aware of the event (NEC clause 61.3).
- If it is late or missed
- Where the contract makes its period a time bar, a compensation event notified late can be lost entirely, time and money.
Drafted from your contract, with its dates checked
£50 + VAT on its own, paid before it is drafted, or included on Autonomous Commercial Management. You check it and serve it.
Draft this documentRead the guide
- How is an NEC compensation event assessed?Under NEC4 the Contractor quotes for a compensation event within three weeks, showing Defined Cost, Fee and delay. The Project Manager replies within two weeks.Guide · NEC contracts
- How to notify a compensation event under NEC4Under NEC4 clause 61.3, notify a compensation event within eight weeks of becoming aware of it, or the Prices and Completion Date may not change.Guide · NEC contracts
- When must an NEC early warning be given?Under NEC4 clause 15.1, give an early warning as soon as you become aware of a matter that could raise the Prices, delay Completion or a Key Date.Guide · NEC contracts