How is an NEC compensation event assessed?
Under NEC4 the Contractor quotes for a compensation event within three weeks, showing Defined Cost, Fee and delay. The Project Manager replies within two weeks.
On this page
Under the NEC4 Engineering and Construction Contract, once the Project Manager instructs quotations for a compensation event, the Contractor submits them within three weeks. Each quotation shows the proposed change to the Prices, assessed from Defined Cost and the resulting Fee, and any delay to the Completion Date and Key Dates, with an altered programme where the event changes it. The Project Manager replies within two weeks, by accepting the quotation, asking for a revised one, or saying it will make its own assessment.
This article describes the NEC4 Engineering and Construction Contract, June 2017 edition with amendments October 2020. Subcontracts and amended versions may differ, so check your own clauses. Notifying the event comes first, and is covered in our guide on notifying a compensation event.
From notification to an instruction to quote
When the Contractor notifies a compensation event, the Project Manager replies within one week, or a longer period the Contractor agrees (clause 61.4). If the event is a compensation event, the reply includes an instruction to submit quotations. If the Project Manager fails to reply, the Contractor may notify that failure, and if it continues for a further two weeks it is treated as acceptance that the event is a compensation event and as an instruction to quote.
What the quotation contains
Clause 62.2 says a quotation comprises the proposed changes to the Prices and any delay to the Completion Date and Key Dates assessed by the Contractor. The Contractor submits details of its assessment with each quotation, and if the event alters the programme for the remaining work, it includes the alterations to the Accepted Programme.
The Project Manager may ask for alternative quotations for different ways of dealing with the event, and the Contractor may offer its own alternatives (clause 62.1).
How the money is assessed
Clause 63.1 assesses the change to the Prices as the effect of the compensation event on the actual Defined Cost of the work done by the dividing date, the forecast Defined Cost of the work not done by the dividing date, and the resulting Fee.
The dividing date depends on the event. For an event arising from an instruction, notification, certificate or changed decision of the Project Manager or the Supervisor, it is the date of that communication. For other events, it is the date the event was notified. Work before that date is priced on what it actually cost, and work after it on a forecast.
The Project Manager and the Contractor may agree rates or lump sums instead (clause 63.2). Clause 63.8 includes risk allowances for matters with a significant chance of occurring that are not compensation events, and clause 63.9 assumes the Contractor reacts competently and promptly.
How the time is assessed
Under clause 63.5, a delay to the Completion Date is the length of time that, because of the event, planned Completion is later than planned Completion shown on the Accepted Programme current at the dividing date. Key Dates are assessed the same way. The assessment takes account of any delay from the event already in the Accepted Programme, and of events between the date of that programme and the dividing date.
That makes the Accepted Programme central. A programme that is out of date or not accepted weakens the time assessment.
The Project Manager's reply
Under clause 62.3 the Project Manager replies within two weeks of the submission. The reply is acceptance of the quotation, an instruction to submit a revised quotation, or notice that the Project Manager will make the assessment. A revised quotation can be asked for only after the reasons are explained, and is due within three weeks (clause 62.4).
If the Project Manager does not reply in time, the Contractor may notify that failure. If the failure continues for a further two weeks after that notification, the quotation is treated as accepted (clause 62.6). Where the Contractor submitted more than one quotation, the notification says which one it proposes to use.
When the Project Manager assesses it
Clause 64.1 lets the Project Manager make the assessment itself, for example where no quotation was submitted in time, or where it decides the quotation was wrong and has not asked for a revision. It must notify its assessment within the time the Contractor had for the quotation, starting when the need becomes apparent (clause 64.3). If it fails to, the Contractor may notify that failure, and after a further two weeks the Contractor's quotation is treated as accepted (clause 64.4).
The event is implemented when a quotation is accepted or treated as accepted, or when the Project Manager notifies its assessment. The Prices, the Completion Date and the Key Dates then change, and the assessment is not revised except as the contract allows (clause 66).
A worked example
Invented example
- Instruction to quote
- Wed 3 Feb 2027
- Quotation submitted
- Mon 22 Feb 2027
- Reply due
- Mon 8 Mar 2027
- Accepted if no reply
- Tue 23 Mar 2027
On an NEC4 contract with a fee percentage of 12%, the Project Manager instructs a change to the Scope on Wednesday 3 February 2027 and, in the same communication, notifies it as a compensation event and instructs a quotation. Because the event arises from the Project Manager's instruction, the dividing date is 3 February 2027, and none of the changed work is done by then.
The quotation is due within three weeks, by Wednesday 24 February 2027. The Contractor submits it on Monday 22 February 2027, with forecast Defined Cost of £18,000.00 and the resulting Fee of £2,160.00, a change to the Prices of £20,160.00, and five days' delay to planned Completion shown on an altered programme.
The Project Manager's reply is due within two weeks of the submission, by Monday 8 March 2027. None arrives, so the Contractor notifies the failure on Tuesday 9 March 2027. If there is still no reply by the end of Tuesday 23 March 2027, the quotation is treated as accepted.
| Item | Basis the notice states | Sum |
|---|---|---|
| Forecast Defined Cost | Work not done at the dividing date of 3 February 2027 | £18,000.00 |
| Resulting Fee | 12% fee percentage in the Contract Data | £2,160.00 |
| Change to the Prices | Defined Cost plus Fee (clause 63.1) | £20,160.00 |
Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.
Questions
Common questions
- How long does the Contractor have to submit a quotation for a compensation event?
- Three weeks from the Project Manager's instruction to submit it, under clause 62.3. A revised quotation is also due within three weeks of the instruction to revise it (clause 62.4). Both can be extended by agreement before they are due (clause 62.5).
- What happens if the Project Manager does not reply to a quotation?
- The Contractor may notify the Project Manager of the failure. If it continues for a further two weeks after that notification, the quotation is treated as accepted (clause 62.6).
- Can a compensation event reduce the Prices?
- Usually not. Clause 63.3 says the Prices are not reduced unless the conditions say so. Clause 63.4 sets out the exceptions, such as a change to the Scope the Contractor proposed and the Project Manager accepted.
Preparing the quotation
Puncheur's compensation event page explains what the notification and quotation contain and how the periods are taken from your own contract.
See the NEC compensation event notification and quotationSources
- NEC4 Engineering and Construction Contract, June 2017 with amendments October 2020, clauses 61.4, 62 to 64 and 66. neccontract.com. Checked 20 November 2026.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.