How to notify a compensation event under NEC4

Under NEC4 clause 61.3, notify a compensation event within eight weeks of becoming aware of it, or the Prices and Completion Date may not change.

Published
19 November 2026
For
Main Contractors and Sub-Contractors
Law checked
19 November 2026
Reading time
4 minutes
On this page
  1. What counts as a compensation event
  2. Who notifies it
  3. The eight-week period
  4. How to give the notice
  5. The Project Manager's reply
  6. Quotations
  7. A worked example
  8. Common questions

Under the NEC4 Engineering and Construction Contract, the Contractor notifies the Project Manager of an event it believes is a compensation event, where the Project Manager has not already notified it. The notice must be given within eight weeks of the Contractor becoming aware that the event has happened. Miss that period and the Prices, the Completion Date and the Key Dates are not changed, unless the event arose from the Project Manager or Supervisor giving an instruction or notification, issuing a certificate or changing an earlier decision.

This article describes the NEC4 Engineering and Construction Contract, June 2017 edition with amendments October 2020. Subcontracts and amended versions may change the periods, so check your own Contract Data and Z clauses.

What counts as a compensation event

The compensation events are listed in clause 60.1, with any additional ones stated in Contract Data part one. They include changes to the Scope instructed by the Project Manager, failures by the Client (NEC4's name for the party paying for the works) or the Project Manager to do things on time, physical conditions an experienced contractor would have judged to have only a small chance of occurring, and weather measured at the place stated in the Contract Data that, for that calendar month, occurs on average less often than once in ten years.

Only an event on the list, or added in the Contract Data, can change the Prices, the Completion Date or a Key Date.

Who notifies it

Where the event arises from the Project Manager or Supervisor giving an instruction or notification, issuing a certificate or changing an earlier decision, clause 61.1 requires the Project Manager to notify the compensation event at the time of that communication.

For other events, the Contractor notifies under clause 61.3. That covers an event which has happened or which it expects to happen, where it believes the event is a compensation event and the Project Manager has not notified it.

The eight-week period

The eight weeks run from when the Contractor becomes aware that the event has happened. It is a strict period. A late notice means no change to the Prices, the Completion Date or the Key Dates, except for events arising from the Project Manager's or Supervisor's own instructions, notifications, certificates or changes of decision.

No compensation event can be notified by either side after the Defects Certificate is issued (clause 61.7).

Because the period runs from awareness, record the date on which the site team first knew of each event. That date is the one that matters if the notice is later said to be late.

How to give the notice

A compensation event notice is a notification, so under clause 13.7 it is communicated separately from other communications. Identify the event, the clause of 60.1 it falls under, the date you became aware of it, and its expected effect on cost and time. If you gave an early warning, refer to it.

The Project Manager's reply

Clause 61.4 requires the Project Manager to reply within one week after the Contractor's notification, or a longer period the Contractor agrees. The reply either confirms that the event is a compensation event and instructs quotations, or states that the Prices, Completion Date and Key Dates are not to be changed, with the reasons.

The reasons it can give are limited. They are that the event arises from a fault of the Contractor, has not happened and is not expected to happen, was not notified within the timescales, has no effect on Defined Cost, Completion or a Key Date, or is not one of the listed compensation events.

If the Project Manager does not reply in time, the Contractor may notify it of that failure. If the failure continues for a further two weeks after that notification, it is treated as acceptance that the event is a compensation event and an instruction to submit quotations.

Quotations

Once instructed, the Contractor submits quotations within three weeks, and the Project Manager replies within two weeks of the submission (clause 62.3). Clause 62.5 lets the two extend these periods by agreement. The quotations show the proposed changes to the Prices and any delay to the Completion Date and Key Dates. If the Project Manager fails to reply to a quotation in time, a similar route applies. The Contractor notifies the failure, and if it continues for a further two weeks the quotation is treated as accepted (clause 62.6).

A worked example

Invented example

Contractor aware
Mon 8 Feb 2027
Last day to notify
Mon 5 Apr 2027
Project Manager reply due
Wed 17 Feb 2027
Deemed acceptance if still no reply
Thu 4 Mar 2027

On Monday 8 February 2027 the Contractor's site team finds that the Client has not allowed access to part of the Site by the later of its access date and the date shown on the Accepted Programme. That is a compensation event under clause 60.1(2). The last day to notify it is Monday 5 April 2027, eight weeks later.

The Contractor notifies it on Wednesday 10 February 2027. The Project Manager's reply is due by Wednesday 17 February 2027. No reply arrives, so the Contractor notifies that failure on Thursday 18 February 2027. If there is still no reply by Thursday 4 March 2027, two weeks later, the event is treated as accepted and quotations as instructed.

Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.

Questions

Common questions

How long do I have to notify a compensation event under NEC4?
Eight weeks from becoming aware that the event has happened. If the Contractor misses it, the Prices, the Completion Date and the Key Dates are not changed, unless the event arises from the Project Manager or Supervisor giving an instruction or notification, issuing a certificate or changing an earlier decision.
How long does the Project Manager have to reply?
One week after the Contractor's notification, or a longer period the Contractor agrees (clause 61.4).
What if the Project Manager does not reply?
The Contractor can notify the Project Manager of its failure. If the failure continues for a further two weeks, it is treated as acceptance that the event is a compensation event and an instruction to submit quotations.

Preparing the notice

Puncheur's NEC compensation event page explains what the notification contains and how the dates are worked out from your contract.

See the NEC compensation event notification and quotation

Sources

  1. NEC4 Engineering and Construction Contract, June 2017 with amendments October 2020, clauses 13.7, 60.1, 61.1, 61.3 to 61.7, 62.3 and 62.6. neccontract.com. Checked 19 November 2026.

A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.