Before you sign
Contract review
A review of your contract or sub-contract before you sign. Each clause that matters is quoted word for word, with its issue, a risk rating and a point to negotiate. You also get a risk register and a schedule of proposed amendments for you to check.
Not legal advice. A competent person must read it and check it against the contract before anyone relies on it or sends it on.
£95 + VATOne-off, no subscription. Upload the contract and any amendments to it.
- Contract review
- Risk register
- Proposed amendments
Payment
Time
Variations
Valuation and cost
Tender and estimating
Timelines
The deadlines, set out.
- 1Valuation dateSet by the contract: JCT interim valuation dates, NEC assessment dates. The payee usually applies by then.
- 2Due dateSet by the contract. Under the Scheme, 7 days after the relevant period ends, or the payee's claim if later (Part II para 4).
- 3Payment NoticeNot later than five days after the due date (s.110A).
- 4Pay Less Notice deadlineThe agreed period before the final date (s.111(5)), or 7 days under the Scheme (Part II para 10).
- 5Final date for paymentThe notified sum must be paid, or the sum in a valid Pay Less Notice (s.111(1) and (6)).
- Payment Notice
- Pay Less Notice window
Miss the window and the notified sum must be paid in full by the final date. Puncheur reads your contract, sets the payment and notice dates in your contract and tells you which side of the line you are on.
- 1Notice of adjudicationAt any time (s.108(2)(a)).
- 2ReferralWithin 7 days of the notice (s.108(2)(b); Scheme para 7(1)).
- 3DecisionWithin 28 days of the referral (s.108(2)(c)).
- 4Extended decisionUp to 14 days more with the referring party's consent, or longer if both agree (s.108(2)(c) and (d)).
- 7 days
- 28 days
Speak to a specialist before you start adjudication, or as soon as one is started against you. Puncheur does not draft adjudication documents.
- 1Delay eventSomething you are not responsible for holds up the work.
- 2NoticePromptly, and within any time bar. Under the NEC4 ECC, eight weeks to notify a compensation event (clause 61.3).
- 3Particulars and estimateThe effects and the extra time, as the contract requires.
- 4Extension of timeDecided within the period the contract sets, if it sets one.
- Time bar
Miss a time bar and the right to more time can be lost. Puncheur marks each time bar it finds in your contract.