Documents · Payment
Payment timetable from the contract
A full-project payment timetable: for every interim payment, the application date, due date, payment notice deadline, first day for a payee's notice in default, final date for payment, Pay Less Notice deadline and earliest suspension date, worked out for you, with bank holidays excluded where the contract or the Construction Act requires. Checks the periods against the Construction Act where it applies.
- When to use it
- When a contract is signed, or when you need every payment date on a project in one place.
- What you get
- For every interim payment, the application date, due date, payment notice deadline, final date for payment, Pay Less Notice deadline and earliest suspension date, with the periods checked against the Construction Act where it applies.
Worked out from your contract
£50 + VAT on its own, paid before it is drafted, or included on Autonomous Commercial Management. You check it before you rely on it or send it on.
Draft this documentRead the guide
- Can I suspend work for non-payment?Yes. If the notified sum is not paid by the final date, you can suspend after at least seven days' notice stating the grounds, under section 112.Guide · Late payment
- How is the final date for payment worked out?The contract sets it. If not, the Scheme makes it 17 days after the due date, leaving out Christmas Day, Good Friday and bank holidays.Guide · Payment
- How to work out the due date for paymentThe due date is when a payment becomes due. Your contract sets it; if not, the Scheme makes it the later of 7 days after the period ends or the claim.Guide · Payment
A guide, not legal advice. The contract’s own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.