Can I suspend work for non-payment?
Yes. If the notified sum is not paid by the final date, you can suspend after at least seven days' notice stating the grounds, under section 112.
On this page
Yes. Under section 112 of the Housing Grants, Construction and Regeneration Act 1996, if the notified sum is not paid in full by the final date for payment, the party owed the money can suspend some or all of its work. It must first give at least seven days' notice of its intention to suspend, stating the grounds. The right applies to a Main Contractor against its Employer and to a Sub-Contractor against its Main Contractor.
These rules apply to construction contracts under Part II of the Act. They do not apply to a contract with a residential occupier for work on their home (section 106), and some operations and some kinds of contract are also excluded (sections 105(2) and 106).
Where the right comes from
Section 112(1) reads as follows.
"Where the requirement in section 111(1) applies in relation to any sum but is not complied with, the person to whom the sum is due has the right (without prejudice to any other right or remedy) to suspend performance of any or all of his obligations under the contract to the party by whom payment ought to have been made (“the party in default”)."
The requirement in section 111(1) is the obligation to pay the notified sum on or before the final date for payment. So the right to suspend follows a failure to pay the notified sum on time. It does not arise from a dispute about value, or from a sum that was validly reduced by a Pay Less Notice and then paid.
The notice comes first
Section 112(2) sets the condition in these words.
"The right may not be exercised without first giving to the party in default at least seven days’ notice of intention to suspend performance, stating the ground or grounds on which it is intended to suspend performance."
Two things follow. The notice must be given before you stop, and it must give at least seven days. It must also state the ground or grounds, which in practice means identifying the payment, the notified sum, the final date and the shortfall.
The safe course is to count the seven days from the day after the notice is given, leaving out Christmas Day, Good Friday and bank holidays as section 116 does. Weekends count.
Check your contract's notices clause for how notices must be served. A notice sent to the wrong address or by a method the contract does not allow invites an argument you do not need.
A worked example
Invented example
- Final date for payment
- Thu 19 Nov 2026
- Notice given
- Fri 20 Nov 2026
- Seven days end
- Fri 27 Nov 2026
- Earliest suspension
- Sat 28 Nov 2026
The final date for payment on a sub-contract is Thursday 19 November 2026. The notified sum is not paid by the end of that day, and no valid Pay Less Notice was given.
The Sub-Contractor gives notice of intention to suspend on Friday 20 November 2026 (by email, received that day), stating the grounds. The seven days start on Saturday 21 November and end on Friday 27 November 2026. No bank holidays fall in that period. The earliest day the Sub-Contractor can suspend is Saturday 28 November 2026.
A notice is given when it is received. Check the contract's notices clause first. Section 115 treats a properly addressed and posted notice as effectively served but gives no deemed date, so send by email or recorded delivery and keep proof of when it arrived.
If the Main Contractor pays the full notified sum before then, the right ceases under section 112(3) and the Sub-Contractor cannot suspend. If it pays after suspension has begun, the right ends on payment in full under section 112(3), and the Sub-Contractor returns to work.
What suspension protects
Suspension has consequences for the programme, and the Act deals with two of them.
Section 112(3A) deals with the cost of suspending, in these words.
"the party in default shall be liable to pay to the party exercising the right a reasonable amount in respect of costs and expenses reasonably incurred by that party as a result of the exercise of the right."
Section 112(4) protects the time position. Any period of suspension is disregarded when working out the time taken to complete the affected work against a contractual time limit, and where the limit is a date, the date is adjusted. That covers the party suspending and any third party whose work is directly or indirectly affected.
Before you suspend
Suspension is a serious step. It can damage a working relationship and, if the conditions are not met, it can put you in breach of contract yourself. Take advice before you stop work, and check these points first.
- The unpaid sum is the notified sum under section 111(2), whether or not the payer disputes it.
- The final date for payment has passed without payment in full.
- No valid Pay Less Notice reduced the sum, or the reduced sum has not been paid either.
- Your notice states the grounds and gives at least seven days, counted under section 116.
- The notice is served in the way your contract allows.
Keep a record of when the notice was given and how, and keep site records from the day you suspend.
What JCT and NEC forms add to the right
JCT and NEC contracts may restate the right to suspend and set how notices must be served. The right to suspend comes from section 112 of the Act, not from the form, so follow the form's notice rules but rely on the Act for the right itself.
Main Contractors as well as Sub-Contractors
The right is often discussed as a Sub-Contractor's remedy, but section 112 applies to any construction contract within Part II of the Act. A Main Contractor whose Employer has not paid the notified sum by the final date has the same right on the main contract, on the same conditions. A Main Contractor considering suspension should also look at how it affects its own sub-contracts.
Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.
Questions
Common questions
- Can I suspend under a JCT or NEC contract?
- Yes. The right to suspend in section 112 applies to JCT, NEC and bespoke construction contracts. Follow the form's rules on how notices are served.
- Do I have to suspend all of the work?
- No. Section 112(1) allows you to suspend performance of any or all of your obligations to the party in default.
- When does the right to suspend end?
- Under section 112(3) it ends when the party in default pays the sum in full. Partial payment does not end it.
- Can I recover the cost of suspending?
- Section 112(3A) makes the party in default liable for a reasonable amount for costs and expenses reasonably incurred as a result of the suspension.
Preparing the notice
Puncheur's notice of intention to suspend page explains what the document states, including the grounds and the earliest suspension date worked out from your dates.
See the Default payment notice / notice of intention to suspend (s.112)Sources
- Housing Grants, Construction and Regeneration Act 1996, section 112. legislation.gov.uk. Checked 18 November 2026.
- Housing Grants, Construction and Regeneration Act 1996, section 111. legislation.gov.uk. Checked 18 November 2026.
- Housing Grants, Construction and Regeneration Act 1996, section 116. legislation.gov.uk. Checked 18 November 2026.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.