Default payment notice / notice of intention to suspend (s.112)
Either a notice that the notified sum was not paid by the final date, demanding payment, or a notice of intention to suspend performance under section 112 stating the grounds, with the earliest suspension date worked out for you.
- When it is due
- When a sum due is not paid in full by the final date for payment and no effective Pay Less Notice was given. At least seven days before suspending (s.112).
- If it is late or missed
- Suspension may start only 7 days after the notice is given (s.112): each day later moves the start back a day.
Drafted from your contract, with its dates checked
£50 + VAT on its own, paid before it is drafted, or included on Autonomous Commercial Management. You check it and serve it.
Draft this documentRead the guide
A guide, not legal advice. The contract’s own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.