A Pay Less Notice tells the payee you will pay less than the notified sum. It must state the sum and how it is worked out, and be given in time.

Published
19 November 2026
For
Main Contractors and Sub-Contractors
Law checked
18 November 2026
Reading time
6 minutes
On this page
  1. Who gives a Pay Less Notice
  2. What the notice must say
  3. When it must be given
  4. What happens if there is no valid notice
  5. A worked example
  6. The Pay Less period in your form
  7. The insolvency exception
  8. Points worth checking
  9. Common questions

A Pay Less Notice is a written notice from the party who pays, saying it intends to pay less than the notified sum. Under section 111 of the Housing Grants, Construction and Regeneration Act 1996 it must state the sum the payer considers due and the basis on which that sum is calculated, and it must be given in time. Without a valid notice given in time, the payer must pay the notified sum by the final date for payment.

These rules apply to construction contracts under Part II of the Act. They do not apply to a contract with a residential occupier for work on their home (section 106), and some operations and some kinds of contract are also excluded (sections 105(2) and 106).

Who gives a Pay Less Notice

The Act talks about the payer and the payee. On most jobs that means an Employer paying a Main Contractor, or a Main Contractor paying a Sub-Contractor. Either of them can be the payer, depending on which contract you are looking at, so the same rules protect a Main Contractor against its Employer and a Sub-Contractor against its Main Contractor.

Section 111(3) allows the notice to come from the payer or from a person named in the contract to give it.

Housing Grants, Construction and Regeneration Act 1996, section 111(3)
"The payer or a specified person may in accordance with this section give to the payee a notice of the payer's intention to pay less than the notified sum."

That specified person is often a contract administrator or quantity surveyor. Check your contract to see who it names.

What the notice must say

Section 111(4) sets out the content. The notice must specify "the sum that the payer considers to be due on the date the notice is served" and "the basis on which that sum is calculated". It ends with this sentence.

Housing Grants, Construction and Regeneration Act 1996, section 111(4)
"It is immaterial for the purposes of this subsection that the sum referred to in paragraph (a) or (b) may be zero."

So a notice that lists deductions without arriving at a sum falls short, and so does a figure with no explanation of how it was reached. The basis does not need to be long, but the payee must be able to see how the payer's figure is calculated, and reconciling it to the notified sum is the clearest way to show that. Contra charges, set-off and disputed measurement all need to appear in that basis if the payer wants to rely on them.

When it must be given

Section 111(5)(a) says the notice "must be given not later than the prescribed period before the final date for payment", which is the period your contract sets or, if it sets none, seven days under paragraph 10 of Part II of the Scheme. Where the notified sum comes from the payee's own notice, section 111(5)(b) also says it "may not be given before the notice by reference to which the notified sum is determined".

Every one of those dates runs from the payment due date, which our guide on how to work out the due date explains.

What happens if there is no valid notice

Section 111(1) is the rule that does the work, and it reads as follows.

Housing Grants, Construction and Regeneration Act 1996, section 111(1)
"Subject as follows, where a payment is provided for by a construction contract, the payer must pay the notified sum (to the extent not already paid) on or before the final date for payment."

If a valid Pay Less Notice is given in time, section 111(6) says that subsection (1) applies only to the sum stated in the notice. If it is not, the full notified sum is payable. Whatever complaints the payer has about the work, it cannot simply withhold the money on this payment.

A worked example

Invented example

Notified sum
£48,000
Pay Less deadline
Thu 12 Nov 2026
Final date for payment
Thu 19 Nov 2026
Sum in the notice
£43,300

A Sub-Contractor's application for November stands as the notified sum at £48,000. The final date for payment is Thursday 19 November 2026, so under the Scheme the last day for a Pay Less Notice is Thursday 12 November 2026. The Main Contractor wants to deduct £3,200 for cleaning it carried out after the Sub-Contractor's gang left the third floor, and £1,500 for a difference in the measured quantity of one item.

A notice that says only "we will deduct contra charges and correct the measurement" does not do what section 111(4) requires, because it states no sum. A notice that says "we consider £43,300 is due" with nothing more does not do it either, because it gives no basis.

A notice that meets the Act, given on Monday 9 November 2026, would state the sum the Main Contractor considers due, £43,300, and show how it gets there. That means the notified sum of £48,000, less £3,200 for the cleaning, with the dates, the location and how the cost was worked out, and less £1,500 for the measurement, with the item, the quantity applied for and the quantity the Main Contractor accepts.

ItemBasis the notice statesSum
Notified sumThe application for November£48,000
Less cleaningThe dates, the location and how the cost was worked out£3,200
Less measurementThe item, the quantity applied for and the quantity accepted£1,500
Sum considered dueStated in the notice£43,300

The Sub-Contractor may still dispute both deductions. But because the notice states a sum and its basis and arrives in time, the Main Contractor need only pay £43,300 by the final date, and the argument about the £4,700 happens separately.

The Pay Less period in your form

The period for a Pay Less Notice is usually set by the contract, whether that is a JCT contract or sub-contract, an NEC contract with Option Y(UK)2, or bespoke terms. Check your payment clause and the contract particulars first. The Scheme's seven days apply only where the contract sets no period.

The insolvency exception

There is one narrow exception. Section 111(10) says subsection (1) does not apply where the contract provides that the payer need not pay if the payee becomes insolvent, and the payee has become insolvent after the prescribed period (that is, after the last day for giving a Pay Less Notice). It is a specific case, not a general escape route.

Points worth checking

Before you rely on a Pay Less Notice, or before you accept one, check these points against your own contract.

  • It was given by the payer or by the person the contract names.
  • It states a sum, even if that sum is zero.
  • It sets out how that sum is calculated.
  • It relates to the payment in question.
  • It arrived within the period the contract sets, or seven days before the final date under the Scheme.
  • It was served in the way the contract's notice clause allows.

If any of these points fails, the payee has grounds to argue that the notice is invalid and the notified sum is payable by the final date.

Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.

Questions

Common questions

Does this apply to JCT and NEC contracts?
Yes. Section 111 applies to JCT, NEC and bespoke construction contracts alike. Those forms usually set their own Pay Less Notice period, and the Scheme's seven days apply only where the contract sets none.
Can a Pay Less Notice say that nothing is due?
Yes. Section 111(4) of the Construction Act says it is immaterial that the sum may be zero, and the notice must still set out the basis on which that sum is calculated (section 111(4)(b)).
What happens if a Pay Less Notice is given late?
The payer must pay the notified sum by the final date for payment; a late notice does not reduce it. Section 111(10) is a separate, narrow exception. Where the contract says the payer need not pay if the payee becomes insolvent, and the payee becomes insolvent after the last day for a Pay Less Notice, the duty to pay does not apply.
Does a Pay Less Notice have to be called a Pay Less Notice?
The Act sets out what the notice must contain and when it must be given. It does not prescribe a title, but a clear heading avoids an argument about what the document was meant to be.

Drafting one from your contract

Puncheur's Pay Less Notice page explains what the document contains and how the payment dates are taken from your own contract.

See the Pay Less Notice

Sources

  1. Housing Grants, Construction and Regeneration Act 1996, section 111. legislation.gov.uk. Checked 18 November 2026.
  2. Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule, Part II. legislation.gov.uk. Checked 18 November 2026.

A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.

See also the terms of use.