Pay Less Notice
A notice of intention to pay less than the notified sum under section 111(3). States the sum considered due on the date of service and its basis, and checks the statutory and contractual deadline against your dates.
- When it is due
- Not later than the period before the final date for payment that the contract sets; if it sets none, seven days before the final date (Scheme, Part II, paragraph 10).
- If it is late or missed
- A late Pay Less Notice does not reduce the notified sum, which must then be paid in full (s.111).
Drafted from your contract, with its dates checked
£50 + VAT on its own, paid before it is drafted, or included on Autonomous Commercial Management. You check it and serve it.
Draft this documentRead the guide
- How to answer a Sub-Contractor's applicationA Main Contractor answers a Sub-Contractor's application with a Payment Notice within 5 days of the due date, and a Pay Less Notice if it will pay less.Guide · Payment
- What is a Pay Less Notice and what must it say?A Pay Less Notice tells the payee you will pay less than the notified sum. It must state the sum and how it is worked out, and be given in time.Guide · Payment
A guide, not legal advice. The contract’s own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.