How to answer a Sub-Contractor's application

A Main Contractor answers a Sub-Contractor's application with a Payment Notice within 5 days of the due date, and a Pay Less Notice if it will pay less.

Published
20 November 2026
For
Main Contractors
Law checked
20 November 2026
Reading time
5 minutes
On this page
  1. Why the Payment Notice matters
  2. The dates under a JCT sub-contract
  3. What to put in the Payment Notice
  4. When you need a Pay Less Notice as well
  5. A worked example
  6. Common questions

When a Sub-Contractor applies for payment, the Main Contractor answers with a Payment Notice not later than 5 days after the due date, stating the sum it considers due and how it is calculated, even if that sum is less than the application or is zero. If it later decides to pay less than the notified sum, it gives a Pay Less Notice not later than the period before the final date that the sub-contract sets. Miss the Payment Notice and the Sub-Contractor's application can become the sum that must be paid.

This article describes the Construction Act and the JCT Design and Build Sub-Contract 2016. Bespoke sub-contracts often change the dates, so check your own.

Why the Payment Notice matters

The Construction Act requires every construction contract to provide for a notice of the sum due, given not later than five days after the payment due date. Under section 110A(2)(a), a payer's notice must specify two things, "the sum that the payer considers to be or to have been due at the payment due date in respect of the payment" and "the basis on which that sum is calculated".

Section 110A(4) adds that it is immaterial that the sum may be zero. A notice saying nothing is due is still a Payment Notice, as long as it gives the basis.

If the payer gives no notice, section 110B lets the payee's own notice stand in its place. Where the contract allows the payee to apply before the payer's notice is due and the payee does so, section 110B(4) treats the application as the payee's notice. That is why an unanswered application can become the notified sum. Our guide on what happens if no Payment Notice is given explains the consequences for the paying side.

The dates under a JCT sub-contract

Under clause 4.6.1 of the JCT Design and Build Sub-Contract 2016, the monthly due date is 12 days after each Interim Valuation Date. The Sub-Contractor may apply so that its Payment Application is received not later than 4 days before the Interim Valuation Date (clause 4.6.3.1), or, where the sub-contract particulars apply clause 4.6.2, must apply each month.

From the due date, the timetable runs as follows.

  • Payment Notice. Not later than 5 days after the due date, stating the sum the Contractor considers to be or to have been due at the due date and the basis on which it has been calculated (clause 4.7.2).
  • Final date for payment. 14 days after the due date (clause 4.7.1).
  • Pay Less Notice. Not later than 5 days before the final date, stating the sum the Contractor considers due at the date of the notice and its basis (clauses 4.7.5 and 4.7.6).

Clause 1.5 applies where an act is required to be done within a specified period of days after or from a specified date, so a Public Holiday inside the Payment Notice period is left out. The Pay Less Notice is counted back from the final date. Our guide on the final date for payment covers the counting.

What to put in the Payment Notice

Value the work on the basis the sub-contract sets, not on the basis of what the Employer has paid you. State the sum you consider due at the due date, then show how it is calculated. A valuation schedule with the gross value, the retention, the sums previously paid and any deduction is the usual way.

Deal with each part of the application you do not accept. A line saying the application is rejected, with no basis, does not meet section 110A(2) and gives the Sub-Contractor an argument that no valid notice was given.

When you need a Pay Less Notice as well

A Payment Notice fixes the notified sum. If you later want to pay less, for example because of a contra charge or a defect found after the Payment Notice, you need a Pay Less Notice in time. Without one, the notified sum must be paid by the final date. Our guide on Pay Less Notices sets out what it must say.

Not being paid by the Employer is not, on its own, a reason to withhold. Section 113(1) of the Construction Act makes a provision ineffective if it makes payment conditional on the payer receiving payment from a third person, unless that third person, or another person further up the chain, is insolvent. If your sub-contract ties payment to the main contract in some other way, take advice on your own clause.

A worked example

Invented example

Application received
Mon 26 Apr 2027
Payment Notice by
Mon 17 May 2027
Pay Less Notice by
Fri 21 May 2027
Final date
Wed 26 May 2027

A Main Contractor has let groundworks on the JCT Design and Build Sub-Contract 2016, with an Interim Valuation Date of Friday 30 April 2027. The Sub-Contractor's application is received on Monday 26 April 2027, 4 days before, so it is in time under clause 4.6.3.1.

The due date is 12 days after the Interim Valuation Date, Wednesday 12 May 2027. The Payment Notice must be given not later than 5 days after that, by Monday 17 May 2027. The final date for payment is 14 days after the due date, Wednesday 26 May 2027, and any Pay Less Notice must be given not later than 5 days before it, by Friday 21 May 2027. The Early May bank holiday, Monday 3 May 2027, falls before the due date, but the due date is a date the sub-contract fixes, not an act, so clause 1.5 does not move it. No Public Holiday falls in the Payment Notice or Pay Less Notice periods.

Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.

Questions

Common questions

Does a Main Contractor have to give a Payment Notice if it disagrees with the application?
Yes. Under clause 4.7.2 of the JCT Design and Build Sub-Contract 2016 the Contractor gives a Payment Notice not later than 5 days after each due date, stating the sum it considers due and the basis. The sum may be zero, but the notice must still be given.
What happens if the Main Contractor gives no Payment Notice?
Under clause 4.7.3, if no Payment Notice is given but a Payment Application has been made, the Contractor must pay the sum in the application, subject to any Pay Less Notice.
When is the Pay Less Notice due under the JCT Design and Build Sub-Contract?
Not later than 5 days before the final date for payment, under clause 4.7.5. It states the sum the Contractor considers due on the date it is given and the basis on which it is calculated.

Answering the application

Puncheur's Payment Notice page explains what the notice contains and how the dates are taken from each sub-contract you let.

See the Payment Notice

Sources

  1. Housing Grants, Construction and Regeneration Act 1996, sections 110A, 110B, 111 and 113. legislation.gov.uk. Checked 20 November 2026.
  2. JCT Design and Build Sub-Contract Conditions 2016, clauses 1.5, 4.6 and 4.7. jctltd.co.uk. Checked 20 November 2026.