Payment Notice
A payer's Payment Notice, a payee's notice required by the contract, or a payee's notice in default under section 110B. States the sum due at the due date and the basis of calculation, with every date worked out for you.
- When it is due
- Not later than five days after the payment due date (s.110A(1)). The contract cannot allow longer.
- If it is late or missed
- A late notice may not count: the sum it states may not become the notified sum.
Drafted from your contract, with its dates checked
£50 + VAT on its own, paid before it is drafted, or included on Autonomous Commercial Management. You check it and serve it.
Draft this documentRead the guide
- How to answer a Sub-Contractor's applicationA Main Contractor answers a Sub-Contractor's application with a Payment Notice within 5 days of the due date, and a Pay Less Notice if it will pay less.Guide · Payment
- How is the final date for payment worked out?The contract sets it. If not, the Scheme makes it 17 days after the due date, leaving out Christmas Day, Good Friday and bank holidays.Guide · Payment
- What happens if no Payment Notice is given?If no Payment Notice is given in time, the payee's own notice or application can become the notified sum, payable unless a Pay Less Notice follows.Guide · Payment