How is the final date for payment worked out?

The contract sets it. If not, the Scheme makes it 17 days after the due date, leaving out Christmas Day, Good Friday and bank holidays.

Published
19 November 2026
For
Main Contractors and Sub-Contractors
Law checked
18 November 2026
Reading time
6 minutes
On this page
  1. The contract comes first
  2. What the Scheme says
  3. Counting the 17 days
  4. Two worked examples
  5. Counting back from the final date
  6. Where your form sets the final date
  7. Why the final date matters
  8. A note on the payee's notice in default
  9. Common questions

The final date for payment is the last day on which a sum that has become due can be paid. Your contract should set it, usually as a number of days after the payment due date. If it does not, the Scheme for Construction Contracts makes it 17 days from the due date, and section 116 of the Construction Act is generally taken to govern the count, so that Christmas Day, Good Friday and bank holidays in England and Wales are left out.

These rules apply to construction contracts under Part II of the Act. They do not apply to a contract with a residential occupier for work on their home (section 106), and some operations and some kinds of contract are also excluded (sections 105(2) and 106).

The contract comes first

Section 110(1) of the Housing Grants, Construction and Regeneration Act 1996 requires every construction contract to do the following.

Housing Grants, Construction and Regeneration Act 1996, section 110(1)
"provide for a final date for payment in relation to any sum which becomes due. The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment."

So the first step is always the payment clause. Look for the due date, which is when a payment becomes due, and the final date, which is the deadline for paying it. They are two different dates, and every other date in the payment cycle hangs off them.

Section 110(3) adds that if or to the extent the contract does not make this provision, the relevant parts of the Scheme apply.

What the Scheme says

Paragraph 8 of Part II of the Scheme deals with the gap in these words.

Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule, Part II, paragraph 8(2)
"The final date for the making of any payment of a kind mentioned in paragraphs 2, 5, 6 or 7, shall be 17 days from the date that payment becomes due."

Paragraphs 2, 5, 6 and 7 cover interim payments, the final payment, the contract price on contracts of under 45 days, and other payments. So the 17 days apply to each of them where the contract is silent.

If the contract also fails to say when payments become due, the Scheme sets that too. For interim payments under paragraph 4, a payment becomes due on the later of the expiry of 7 days following the relevant period, or the making of a claim by the payee.

Counting the 17 days

Section 116(2) says a period "after or from" a date begins immediately after that date. So the day the payment becomes due is not counted; day one is the next day.

Section 116(3) then leaves out Christmas Day, Good Friday and any day that is a bank holiday in England and Wales under the Banking and Financial Dealings Act 1971. Weekends are counted as ordinary days.

Your contract may have its own rules for counting days. If it does, they will usually govern dates set by the contract. Where a date also matters under the Act, such as the final date and the Pay Less Notice deadline, work it out both ways and act by the earlier date if you are the one who has to act.

Two worked examples

Invented example

November due date
Mon 2 Nov 2026
November final date
Thu 19 Nov 2026
December due date
Fri 11 Dec 2026
December final date
Wed 30 Dec 2026

Take a contract that makes the November payment due on Monday 2 November 2026 and says nothing about the final date. Counting 17 days from the day after the due date, with no bank holidays in the way, the final date for payment is Thursday 19 November 2026.

Now take the same contract with a payment due on Friday 11 December 2026. Christmas Day on Friday 25 December 2026 and the Boxing Day bank holiday on Monday 28 December 2026 fall inside the 17 days, so both are left out. The final date for payment is Wednesday 30 December 2026. Counting every calendar day would give Monday 28 December, which is two days early and is itself a bank holiday.

Counting back from the final date

Under paragraph 10 of Part II of the Scheme, where the contract sets no period, a Pay Less Notice must be given not later than seven days before the final date. Counting back is less settled than counting forward.

In the December example, counting seven days back from Wednesday 30 December 2026, and leaving out 25 and 28 December again, gives Monday 21 December 2026. Counting back on plain days gives Wednesday 23 December 2026. We are not aware of a decided case that settles which is right. The doubt arises because section 116(2) speaks of a period "after or from" a date.

For the payer, work to Monday 21 December. For the payee, a notice that arrives on Tuesday 22 or Wednesday 23 December may be in time on one reading, so take advice before treating it as late. A notice that arrives on Thursday 24 December or later is late on either reading.

Where your form sets the final date

JCT contracts and sub-contracts, NEC contracts with Option Y(UK)2, and many bespoke forms set the final date as a number of days after the due date. Read the payment clause and the contract particulars. The Scheme's 17 days apply only where the contract gives no final date.

Why the final date matters

Several of the payment rules in the Act are measured from the final date.

Under section 111(1) the payer must pay the notified sum on or before it. A Pay Less Notice must be given not later than the prescribed period before it, which is seven days under paragraph 10 of the Scheme where the contract sets no period. If the final date passes without payment of the notified sum in full, the payee can give notice of intention to suspend under section 112, and statutory interest under the Late Payment of Commercial Debts (Interest) Act 1998 may start to run, depending on the contract.

Get the final date wrong and every one of those dates moves with it. For a payer, that can mean a Pay Less Notice served a day late. For a payee, it can mean a suspension notice served a day early.

A note on the payee's notice in default

If the payer gives no Payment Notice and the payee gives its own notice late, section 110B(3) postpones the final date by the number of days the payee's notice was late (counted to the day the notice is given, normally the day it is received). A notice is given when it is received. Check the contract's notices clause first. Section 115 treats a properly addressed and posted notice as effectively served but gives no deemed date, so send by email or recorded delivery and keep proof of when it arrived. Where that happens, work the later dates from the postponed final date, not the original one.

Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.

Questions

Common questions

What is the final date for payment under JCT or NEC?
JCT, NEC and bespoke contracts set their own final date for payment, usually as a number of days after the due date. Read your payment clause and contract particulars; the Scheme's 17 days apply only where the contract gives no final date.
Is the final date the same as the due date?
No. The due date is when the sum becomes due. The final date is the last day for paying it, and the Act requires every construction contract to provide one.
Can the contract set any period between the due date and the final date?
Section 110(1) says the parties are free to agree how long the period is. The Scheme's 17 days apply only where the contract provides no final date.
Does the 17 days include weekends?
Yes. Under section 116 only Christmas Day, Good Friday and bank holidays are left out. Saturdays and Sundays count.

Setting out every date

Puncheur's payment timetable page explains how each due date, notice deadline and final date is worked out from your contract, with bank holidays left out where the Act or the contract requires.

See the Payment timetable from the contract

Sources

  1. Housing Grants, Construction and Regeneration Act 1996, section 110. legislation.gov.uk. Checked 18 November 2026.
  2. Housing Grants, Construction and Regeneration Act 1996, section 116. legislation.gov.uk. Checked 18 November 2026.
  3. Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule, Part II. legislation.gov.uk. Checked 18 November 2026.
  4. Bank holidays in England and Wales, GOV.UK. gov.uk. Checked 18 November 2026.

A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.