How to work out the due date for payment
The due date is when a payment becomes due. Your contract sets it; if not, the Scheme makes it the later of 7 days after the period ends or the claim.
On this page
The due date is the date on which a payment becomes due under a construction contract. Your contract should fix it, usually as a set number of days after the valuation date or the application. If it does not, the Scheme for Construction Contracts makes an interim payment due on the later of the expiry of 7 days after the end of the relevant period and the making of the payee's claim.
These rules apply to construction contracts under Part II of the Act. They do not apply to a contract with a residential occupier for work on their home (section 106), and some operations and some kinds of contract are also excluded (sections 105(2) and 106).
Why the due date comes first
Every other date in a payment cycle runs from the due date. Section 110A of the Housing Grants, Construction and Regeneration Act 1996 requires a Payment Notice "not later than five days after the payment due date". The final date for payment is set by reference to the due date, and the last day for a Pay Less Notice is then counted back from the final date.
Get the due date wrong and every later date moves with it. That is true for a Main Contractor valuing a Sub-Contractor's work and for an Employer paying a Main Contractor.
Section 110A(6) defines it simply. The "payment due date" means "the date provided for by the contract as the date on which the payment is due".
How contracts fix it
Section 110(1)(a) requires every construction contract to "provide an adequate mechanism for determining what payments become due under the contract, and when". Contracts do this in different ways. Some say a payment becomes due a set number of days after a monthly valuation date. Some tie it to the receipt of the payee's application. Others list the due dates in the contract particulars or a payment schedule.
Read the payment clause and the particulars together, because the dates are often split between them. A sub-contract order may also change the dates in the standard terms it refers to.
There is one thing a contract cannot do. Section 110(1D) says the mechanism is not adequate where the contract provides for the due date "to be determined by reference to the giving to the person to whom the payment is due of a notice which relates to what payments are due under the contract". A due date that only arrives when the payer issues its own valuation to the payee does not comply, and the Scheme fills the gap.
What the Scheme says
Where the contract does not provide an adequate mechanism, paragraph 3 of Part II of the Scheme brings in paragraphs 4 to 7. For interim payments, paragraph 4 says a payment "shall become due on whichever of the following dates occurs later". The two dates are "the expiry of 7 days following the relevant period mentioned in paragraph 2(1) above" and "the making of a claim by the payee". This applies to interim payments on a contract expected to last 45 days or more. The final payment, and payment on a shorter contract, have their own rules in paragraphs 5 and 6, which also wait for the payee's claim.
Two definitions in paragraph 12 matter here. The relevant period is the period set by or calculated from the contract or, failing that, "a period of 28 days". A claim by the payee means "a written notice given by the party carrying out work under a construction contract to the other party specifying the amount of any payment or payments which he considers to be due and the basis on which it is, or they are calculated".
So under the Scheme, the payee's claim matters. Until a written claim with a sum and its basis is made, the payment does not become due, however long ago the period ended. The money is not lost. It becomes due once the claim is made.
A worked example
Invented example
- Period ends
- Sat 31 Oct 2026
- Claim made
- Mon 2 Nov 2026
- Due date
- Sat 7 Nov 2026
- Final date for payment
- Tue 24 Nov 2026
A sub-contract says the work is valued monthly to the last day of each month, but it says nothing about when payment becomes due or about the final date. The Scheme fills both gaps.
The October period ends on Saturday 31 October 2026. Seven days following it expire on Saturday 7 November 2026. The Sub-Contractor sends its claim, with the sum and how it is calculated, on Monday 2 November 2026. The later of the two dates is Saturday 7 November, so that is the due date.
From there the Main Contractor's Payment Notice is due by Thursday 12 November 2026, and the final date for payment, 17 days from the due date under paragraph 8, is Tuesday 24 November 2026. A Pay Less Notice must be given by Tuesday 17 November 2026.
Now suppose the Sub-Contractor sends its claim late, on Wednesday 11 November 2026. The claim is now the later date, so the payment becomes due on Wednesday 11 November. The Payment Notice deadline moves to Monday 16 November 2026, the final date to Saturday 28 November 2026 and the last day for a Pay Less Notice to Saturday 21 November 2026. A late application costs the payee four days at every stage.
Due dates in JCT, NEC and purchase orders
JCT contracts and sub-contracts, and NEC contracts, fix due dates by reference to valuation or assessment dates in the contract particulars or a payment schedule. NEC contracts meet the Act's payment rules through Option Y(UK)2, so check that it is included. The Scheme's due date applies only where the contract, often a bespoke form or purchase order, has no adequate mechanism.
Common mistakes
It is easy to confuse three different dates. The valuation date is the date the work is measured to. The due date is when the payment becomes due. The final date is the last day for paying it. A contract may set all three, or only some, and they are rarely the same day.
Weekends count. Section 116 leaves out Christmas Day, Good Friday and bank holidays in England and Wales only where something must be done within a period "after or from" a date, such as the Payment Notice or paying by the final date, and that period begins on the following day. The Scheme's due date is not such a period, so it counts every day and can fall on a bank holiday.
The Scheme's 7 days run from the end of the relevant period, not from the date of the application. And under the Scheme a payment cannot become due before the payee's claim is made, so an application that never goes in leaves the payment without a due date until one is made.
Finally, the contract's own terms come first. The Scheme applies only to the extent the contract does not provide an adequate mechanism, so read the contract before reaching for paragraph 4.
Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.
Questions
Common questions
- How do JCT and NEC contracts set the due date?
- Standard forms such as JCT and NEC fix due dates by reference to valuation or assessment dates in the contract particulars or a schedule. The Scheme's due date applies only where the contract has no adequate mechanism.
- Is the due date the date I get paid?
- No. The due date is when the payment becomes due. The payer then has until the final date for payment to pay it, and the Payment Notice and Pay Less Notice deadlines sit between the two.
- Can a late application change the due date?
- Under the Scheme, yes. An interim payment becomes due on the later of the end of 7 days after the relevant period and the making of the payee's claim, so a late claim makes a later due date.
- Can the contract make the due date depend on a certificate?
- Not if the date depends on a notice given to the payee about what is due. Section 110(1D) says that does not provide an adequate mechanism, and the Scheme then applies.
Setting out the dates
Puncheur's payment timetable page explains how each due date, notice deadline and final date is worked out from your contract, with the clause or Scheme paragraph each one comes from.
See the Payment timetable from the contractSources
- Housing Grants, Construction and Regeneration Act 1996, section 110. legislation.gov.uk. Checked 18 November 2026.
- Housing Grants, Construction and Regeneration Act 1996, section 110A. legislation.gov.uk. Checked 18 November 2026.
- Housing Grants, Construction and Regeneration Act 1996, section 116. legislation.gov.uk. Checked 18 November 2026.
- Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule, Part II. legislation.gov.uk. Checked 18 November 2026.
- Bank holidays in England and Wales, GOV.UK. gov.uk. Checked 18 November 2026.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.