Guides · Payment
What happens if no Payment Notice is given?
If no Payment Notice is given in time, the payee's own notice or application can become the notified sum, payable unless a Pay Less Notice follows.
On this page
If the payer does not give a Payment Notice in time, the payee can give its own notice stating the sum it considers due, and that sum becomes the notified sum. Where the contract lets the payee apply before the payer's notice is due, a valid application already counts as that notice. The payer must then pay it by the final date unless it gives a valid Pay Less Notice in time.
These rules apply to construction contracts under Part II of the Act. They do not apply to a contract with a residential occupier for work on their home (section 106), and some operations and some kinds of contract are also excluded (sections 105(2) and 106).
The Payment Notice the payer should give
Section 110A of the Housing Grants, Construction and Regeneration Act 1996 requires every construction contract to deal with a notice for each payment. Usually that is the payer's notice, which must be given "not later than five days after the payment due date" and must state the sum the payer considers due and the basis on which it is calculated.
If the contract does not deal with this properly, paragraph 9 of Part II of the Scheme for Construction Contracts applies. It says that the payer "must, not later than five days after the payment due date, give a notice to the payee".
The payer here might be an Employer paying a Main Contractor, or a Main Contractor paying a Sub-Contractor. The rules are the same on both contracts.
When the payer gives nothing
Section 110B deals with the payer's silence. It applies where the contract requires the payer to give a notice not later than five days after the due date, and "notice is not given as so required".
Section 110B(2) then gives the payee a remedy.
"Subject to subsection (4), the payee may give to the payer a notice complying with section 110A(3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the contract to be given."
A notice complying with section 110A(3) states the sum the payee considers due at the payment due date and the basis on which it is calculated. This is often called a notice in default.
Section 111(2)(c) then makes the sum in that notice the notified sum. Under section 111(1) the payer must pay it on or before the final date for payment, unless a valid Pay Less Notice reduces it.
When the application already counts
Many contracts ask the payee to apply for payment before the payer's notice is due. Section 110B(4) deals with that case. It applies where the contract "permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer or a specified person" of the sum it considers will become due and the basis of calculation, and "the payee gives such notification in accordance with the contract". In that case, the subsection goes on as follows.
"that notification is to be regarded as a notice complying with section 110A(3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection)."
So if your application was made on time and in the form the contract asks for, and it states the sum and how it is calculated, it already stands as your notice. You do not need to send a second one, and the subsection says you may not.
If the contract has no such step, or the application did not meet it, the payee gives a fresh notice under section 110B(2).
The final date moves if the notice is late
Giving a notice in default late does not lose the payment, but it delays it. Section 110B(3) reads as follows.
"Where pursuant to subsection (2) the payee gives a notice complying with section 110A(3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date referred to in subsection (2) that the notice was given."
The count runs to the day the notice is given, which normally means the day it is received. A notice sent by post is given when it arrives, so the postponement is longer than the date on the letter suggests.
The sooner the notice goes in, the less the final date moves.
A worked example
Invented example
- Payer's notice due
- Sat 7 Nov 2026
- Notice in default given
- Wed 11 Nov 2026
- Postponed final date
- Mon 23 Nov 2026
- Pay Less deadline
- Mon 16 Nov 2026
Take a contract where the payment due date is Monday 2 November 2026 and the payer's Payment Notice is due not later than five days later, by Saturday 7 November 2026. The final date for payment is Thursday 19 November 2026. The contract has no application step before the payer's notice.
No Payment Notice arrives. The payee gives its notice in default on Wednesday 11 November 2026 (by email, so it is received that day), four days after the payer's deadline. Under section 110B(3) the final date moves four days later, to Monday 23 November 2026.
The payer can still give a Pay Less Notice, but it must do so not later than the prescribed period before the new final date and, under section 111(5)(b), not before the payee's notice was given, so here between 11 and 16 November. Under the Scheme's seven days, the last day is Monday 16 November 2026. If no valid Pay Less Notice arrives, the sum in the payee's notice is payable by 23 November.
A notice is given when it is received. Check the contract's notices clause first. Section 115 treats a properly addressed and posted notice as effectively served but gives no deemed date, so send by email or recorded delivery and keep proof of when it arrived.
Who gives the Payment Notice under your form
Standard forms such as JCT and NEC say who gives the Payment Notice and whether the payee's application counts as its notice. That decides whether section 110B(4) applies, so read the payment clause before sending a separate notice in default.
What to put in the notice
The notice needs to do what section 110A(3) asks. State the sum you consider due at the payment due date, and set out the basis on which it is calculated. A valuation that shows the gross value, the retention, the sums already paid and the resulting figure will usually do that. Keep the notice to the payment in question and serve it in the way the contract's notice clause allows.
Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.
Questions
Common questions
- Does my application count as a notice in default?
- It can. Under section 110B(4), if the contract permits or requires the payee to notify the sum before the payer's notice is due, and the payee does so in line with the contract, that notification is treated as the payee's notice.
- Can the payer still pay less after missing its Payment Notice?
- Yes, but only with a valid Pay Less Notice given in time under section 111. Without one, the sum in the payee's notice is payable by the final date.
- Does a late notice in default lose the payment?
- No. Section 110B(2) lets the payee give its notice at any time after the payer's deadline. The final date moves later by the number of days it was late.
Preparing the notice
Puncheur's Payment Notice page explains what the document contains, for the payer giving its notice and for the payee giving one in default.
See the Payment NoticeSources
- Housing Grants, Construction and Regeneration Act 1996, section 110A. legislation.gov.uk. Checked 18 November 2026.
- Housing Grants, Construction and Regeneration Act 1996, section 110B. legislation.gov.uk. Checked 18 November 2026.
- Housing Grants, Construction and Regeneration Act 1996, section 111. legislation.gov.uk. Checked 18 November 2026.
- Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule, Part II. legislation.gov.uk. Checked 18 November 2026.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.