Guides · Late payment
Late payment interest in construction contracts
Interest is usually due. Without a substantial contract remedy, the Late Payment Act adds 8% over Bank Rate plus £40 to £100 compensation.
On this page
Interest on late payment is usually available under the Late Payment Act. A construction contract between two businesses is a contract for the supply of goods or services, so the Late Payment of Commercial Debts (Interest) Act 1998 can add simple interest at 8% a year over Bank Rate to a sum paid late, plus a fixed sum of £40, £70 or £100. If your contract sets its own interest rate and that rate is a substantial remedy, the contract rate applies instead.
Does the Act apply to your contract
Section 2(1) says the Act applies in the following case.
"to a contract for the supply of goods or services where the purchaser and the supplier are each acting in the course of a business, other than an excepted contract."
A sub-contract between a Main Contractor and a Sub-Contractor, or a building contract between a commercial Employer and a Main Contractor, will normally fall within that. Work for a homeowner acting as a consumer does not, because the purchaser is not acting in the course of a business.
Section 1(1) then implies the term in these words.
"It is an implied term in a contract to which this Act applies that any qualifying debt created by the contract carries simple interest subject to and in accordance with this Part."
When the contract has its own interest clause
Many construction contracts include an interest clause. The Act deals with that in section 8. Section 8(2) provides as follows.
"Where the parties agree a contractual remedy for late payment of the debt that is a substantial remedy, statutory interest is not carried by the debt (unless they agree otherwise)."
Section 9 says a remedy is to be regarded as substantial unless it is insufficient to compensate the supplier or deter late payment, and it would not be fair or reasonable to allow it to oust or vary statutory interest. Under section 8(4), a contractual right to interest that is not a substantial remedy is void to that extent, unless the overall remedy is substantial.
So read your contract first. If it sets a rate that is a substantial remedy, that rate governs (section 8(2)), and whether it is substantial is judged under section 9. If the clause is missing, or the rate is so low that it neither compensates nor deters, statutory interest may apply instead.
Interest clauses in JCT and NEC forms
JCT and NEC contracts often include their own interest provision. Whether it displaces statutory interest depends on whether it is a substantial remedy under sections 8 and 9, so check the rate your form sets.
When interest starts and the rate
Section 4(2) says statutory interest "starts to run on the day after the relevant day for the debt". Where there is an agreed payment day, that is generally the relevant day. On a construction contract the final date for payment is the natural candidate, as it is the last day for payment, but check how your contract words it.
Section 4 also has rules for long payment terms. Where the purchaser is not a public authority and the agreed payment day falls more than 60 days after the later of the work being done and the purchaser having notice of the sum, interest can start earlier unless the agreed day is not grossly unfair to the supplier (sections 4(2E) and 4(2F)). The limit is 30 days where the purchaser is a public authority (section 4(2D)).
The rate is set by article 4 of the Late Payment of Commercial Debts (Rate of Interest) (No. 3) Order 2002.
"The rate of interest for the purposes of the Late Payment of Commercial Debts (Interest) Act 1998 shall be 8 per cent per annum over the official dealing rate in force on the 30th June (in respect of interest which starts to run between 1st July and 31st December) or the 31st December (in respect of interest which starts to run between 1st January and 30th June) immediately before the day on which statutory interest starts to run."
The official dealing rate is the Bank of England's Bank Rate. The Bank's published record shows Bank Rate at 3.75% from 18 December 2025 until 4 November 2026 (it rose to 4.00% on 5 November 2026), so it was 3.75% on 30 June 2026. Interest that starts to run between 1 July and 31 December 2026 is therefore at 11.75% a year. Interest that starts to run from 1 January 2027 uses Bank Rate on 31 December 2026. This rate was checked on 18 November 2026 and is due for review on 1 January 2027.
Fixed compensation as well
Once statutory interest begins to run, section 5A(1) entitles the supplier to a fixed sum "in addition to the statutory interest on the debt". Section 5A(2) sets the amount, "the sum of £40" for a debt less than £1000, "the sum of £70" for a debt of £1000 or more but less than £10,000, and "the sum of £100" for a debt of £10,000 or more.
Section 5A(2A) adds that if the reasonable costs of recovering the debt are more than the fixed sum, the supplier can also claim the difference.
A worked example
Invented example
- Notified sum
- £20,000
- Interest for 32 days
- £206.03
- Fixed compensation
- £100
- Total claimed
- £306.03
A Sub-Contractor's notified sum of £20,000 has a final date for payment of Thursday 19 November 2026. The sub-contract has no interest clause. The Main Contractor pays the full sum on Monday 21 December 2026.
Statutory interest starts to run on Friday 20 November 2026 at 11.75% a year, simple. That is about £6.44 a day on £20,000. Interest runs from 20 November to the day of payment on 21 December, counting both days, as Puncheur's calculator does. That is 32 days, giving interest of £206.03. Because the debt is £10,000 or more, the Sub-Contractor can also claim fixed compensation of £100 under section 5A, a total of £306.03.
The same rules apply when a Main Contractor is paid late by its Employer, subject to what the main contract says about interest.
What to do with this
Interest is easy to forget when the money finally arrives. Work it out at the time, send a short letter that states the debt, the dates, the rate and the total, and keep it with the payment records. If your contract has its own rate, use that rate and quote the clause.
Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.
Questions
Common questions
- Does a JCT or NEC interest clause replace statutory interest?
- It can. If the contract's interest provision is a substantial remedy, it replaces statutory interest under section 8(2). If it is not, statutory interest can still apply.
- What rate is statutory interest?
- 8% a year over the Bank of England's official dealing rate, Bank Rate, in force on 30 June or 31 December before interest starts. For interest starting between 1 July and 31 December 2026 that is 11.75%.
- Is statutory interest simple or compound?
- Simple. Section 1(1) of the Late Payment Act says a qualifying debt carries simple interest.
- Can I claim interest if my contract sets its own rate?
- If the contract rate is a substantial remedy, it replaces statutory interest under section 8(2). If it is not, the term is void to that extent and statutory interest can apply.
Working out the figure
Puncheur's free late payment calculator works out statutory interest and fixed compensation from the sum, the final date and the date paid.
Open the late payment calculatorSources
- Late Payment of Commercial Debts (Interest) Act 1998, section 1. legislation.gov.uk. Checked 18 November 2026.
- Late Payment of Commercial Debts (Interest) Act 1998, section 2. legislation.gov.uk. Checked 18 November 2026.
- Late Payment of Commercial Debts (Interest) Act 1998, section 4. legislation.gov.uk. Checked 18 November 2026.
- Late Payment of Commercial Debts (Interest) Act 1998, section 5A. legislation.gov.uk. Checked 18 November 2026.
- Late Payment of Commercial Debts (Interest) Act 1998, section 8. legislation.gov.uk. Checked 18 November 2026.
- Late Payment of Commercial Debts (Interest) Act 1998, section 9. legislation.gov.uk. Checked 18 November 2026.
- Late Payment of Commercial Debts (Rate of Interest) (No. 3) Order 2002, article 4. legislation.gov.uk. Checked 18 November 2026.
- Bank of England, Bank Rate history. bankofengland.co.uk. Checked 18 November 2026.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.