What goes in a JCT extension of time application
A JCT extension of time claim needs the Relevant Event, its effect on completion, an estimate of delay and updates, under clauses 2.27 to 2.29.
On this page
Under a JCT contract, an extension of time application is made up of the notice of delay, the particulars of each delaying event and an estimate of its effect on completion, with updates as the delay develops. To succeed, it must show that a Relevant Event listed in clause 2.29 is likely to delay completion beyond the Completion Date. The Architect/Contract Administrator then fixes a later Completion Date that it estimates to be fair and reasonable.
This article describes the JCT Standard Building Contract 2016 and 2024 editions, and the JCT Design and Build Sub-Contract 2016 for Sub-Contractors. Many JCT contracts are amended, so check your own clauses. Our guide on giving notice of delay under JCT covers the notice itself.
The test the decision applies
Clause 2.28.1 sets out two questions for the Architect/Contract Administrator. Is any of the events stated to be a cause of delay a Relevant Event? And is completion of the works, or a section, likely to be delayed by it beyond the relevant Completion Date?
If the answer to both is yes, it must give an extension by fixing a later Completion Date it estimates to be fair and reasonable. Everything in the application should be aimed at those two questions.
Name the Relevant Event
Start with the cause, and then match it to the clause. The Relevant Events in clause 2.29 of the 2016 Standard Building Contract include Variations, certain instructions of the Architect/Contract Administrator, deferment of possession, impediment or prevention by the Employer and its people, work by statutory undertakers, exceptionally adverse weather, Specified Perils, strikes and force majeure.
Cite the sub-clause you rely on, for example 2.29.1 for a Variation or 2.29.6 for an impediment by the Employer. Where more than one event is involved, deal with each separately. Clause 2.28.3 requires the decision to state the extension attributed to each Relevant Event, so an application that keeps them apart is easier to decide.
Show the effect on completion
This is where most of the work lies. The application should explain how the event affects the work that drives completion, not just the work it touches. A two-week delay to a finishing trade that has spare time before completion may not move the Completion Date at all.
The usual evidence is the programme. Show the planned sequence, the activities the event affected, and how that pushes out the completion of the works or the section. Keep the dates in the application consistent with the programme you submit with it.
Clause 2.27.2 asks for particulars of the expected effects, including an estimate of any expected delay to completion. Give a figure, explain how you reached it, and say what you have assumed.
Keep it up to date
Delays change. Clause 2.27.3 requires the Contractor to notify any material change in the estimated delay or the other particulars. Under the 2016 edition it must also supply further information the Architect/Contract Administrator reasonably requires. Under the 2024 edition, requests for further information are made under clause 2.27.4.
Under the 2024 edition, clause 2.27.4 also allows the Architect/Contract Administrator to ask for further information not later than 14 days after receiving the particulars or a notification of change. The 8-week decision period in clause 2.28.2 of that edition can then run from receipt of that further information. Under the 2016 edition, the decision period is 12 weeks from receipt of the required particulars.
Show you have tried to limit the delay
Clause 2.28.6.1 requires the Contractor to use its best endeavours to prevent delay, however caused, and to prevent completion being delayed or further delayed. Clause 2.28.6.2 requires it to do all that may reasonably be required to proceed with the works.
An application that records what was done to reduce the delay, such as re-sequencing or moving resources, answers that point before it is raised.
Sub-Contractors under a JCT sub-contract
The JCT Design and Build Sub-Contract 2016 follows the same structure. Clauses 2.17 and 2.18 deal with the notice, particulars and decision, and the Relevant Sub-Contract Events are in clause 2.19. The Contractor fixes the revised period for completion and must notify its decision within 16 weeks of receiving the required particulars.
A Sub-Contractor's application goes to the Contractor, not the Architect/Contract Administrator. A Main Contractor will often need the Sub-Contractor's particulars to support its own application under the main contract, so prompt and complete particulars help both.
A worked example
Invented example
- Variation instructed
- Tue 1 Jun 2027
- Particulars received
- Wed 2 Jun 2027
- Information request deadline
- Wed 16 Jun 2027
- Decision due, if no request
- Wed 28 Jul 2027
On a Standard Building Contract, a Variation instructed on Tuesday 1 June 2027 adds a plant room to the roof. The Contractor gives notice the same day and sends its particulars on Wednesday 2 June 2027, by email, received that day. These identify clause 2.29.1, show on the programme that roof completion drives the Completion Date, and estimate three weeks' delay.
Under the 2024 edition, the Architect/Contract Administrator may ask for further information by Wednesday 16 June 2027. If it asks for none, its decision is due by Wednesday 28 July 2027. Two weeks later the roofing subcontractor reports a further week's delay, and the Contractor notifies the change under clause 2.27.3 with a revised estimate.
Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.
Questions
Common questions
- Is an extension of time application separate from the notice of delay?
- Under JCT the two run together. Clause 2.27.1 is the notice, clause 2.27.2 the particulars and estimate, and clause 2.27.3 the updates. Together they form what most people call the extension of time application.
- Do I have to show the delay affects completion?
- Yes. The Architect/Contract Administrator fixes a later Completion Date only if a Relevant Event is likely to delay completion beyond the current Completion Date (clause 2.28.1).
- Does the Contractor have to try to reduce the delay?
- Yes. Clause 2.28.6.1 requires the Contractor to use its best endeavours to prevent delay and to prevent completion being delayed or further delayed.
Preparing the application
Puncheur's extension of time application page explains what the document contains and how it follows on from the notice of delay.
See the Extension of time applicationSources
- JCT Standard Building Contract Without Quantities 2016, clauses 2.27, 2.28, 2.29. jctltd.co.uk. Checked 19 November 2026.
- JCT Standard Building Contract With Quantities 2024, clauses 2.27.4 and 2.28.2. jctltd.co.uk. Checked 19 November 2026.
- JCT Design and Build Sub-Contract Conditions 2016, clauses 2.17 to 2.19. jctltd.co.uk. Checked 19 November 2026.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.