Under JCT the final account follows set periods after practical completion. A Sub-Contractor must dispute the statement within one month or it is deemed agreed.

Published
20 November 2026
For
Main Contractors and Sub-Contractors
Law checked
20 November 2026
Reading time
4 minutes
On this page
  1. Under a JCT main contract
  2. Why the Final Certificate matters
  3. Under a JCT sub-contract
  4. What to put in the final account
  5. A worked example
  6. Common questions

Under a JCT contract the final account follows a fixed sequence after practical completion. The Contractor or Sub-Contractor sends the documents needed to calculate the final sum, the other side prepares a statement of the adjustments, and a final certificate or Final Payment Notice follows. Each step has a period, and the last ones have teeth. A statement not disputed in time can be deemed agreed, and a final certificate or notice not challenged in time becomes conclusive.

This article describes the JCT Standard Building Contract Without Quantities 2016 and the JCT Design and Build Sub-Contract 2016. Many contracts are amended, so check the periods in your own copy.

Under a JCT main contract

Clause 4.25.1 of the Standard Building Contract requires the Contractor to provide all documents necessary for adjusting the Contract Sum not later than 6 months after the Practical Completion Certificate, or the last Section Completion Certificate.

Not later than 3 months after receiving them, the Quantity Surveyor prepares a statement of all adjustments to the Contract Sum, and any loss and expense notified but not yet ascertained is ascertained. The Architect/Contract Administrator sends the Contractor copies within that 3 month period (clause 4.25.2). If the Contractor has not supplied the documents after 6 months, the Architect/Contract Administrator can give one month's notice requiring them, and then complete the statement on the information it has (clause 4.25.3).

The Final Certificate follows under clause 4.26.1, not later than 2 months after the last of the end of the Rectification Period, the Certificate of Making Good, and the sending of the statement. It states the adjusted Contract Sum and the amounts already certified, and the final payment is the difference.

Why the Final Certificate matters

Clause 1.9.1 makes the Final Certificate conclusive evidence in any later adjudication, arbitration or court proceedings on several matters. They include that all terms requiring an adjustment to the Contract Sum have been given effect, apart from an erroneous inclusion or exclusion or an arithmetical error, that all extensions of time due have been given, and that the reimbursement of loss and expense is in final settlement of claims arising from the Relevant Matters.

That effect is suspended for proceedings started before, or within 28 days after, the Final Certificate is issued (clause 1.9.2). A Contractor who disagrees with the final account has to act within that window.

Under a JCT sub-contract

The JCT Design and Build Sub-Contract 2016 runs to tighter periods for the Sub-Contractor. Under clause 4.21.1, it sends the Contractor all documents necessary for calculating the Final Sub-Contract Sum not later than 2 months after practical completion of the Sub-Contract Works. The Contractor then has up to 8 months from receipt to send a statement of the calculation (clause 4.21.2). If the documents do not arrive within the 2 months, the Contractor prepares a statement on the information it has (clause 4.21.3).

The key period for the Sub-Contractor is in clause 4.21.4. If nothing in the Contractor's statement is disputed in writing, giving grounds, within one month of its submission, the Final Sub-Contract Sum is deemed to have taken into account all the adjustments the conditions require. Silence for a month can settle the account.

The final payment then falls due 2 months after the last of the Retention Release Date, any later retention release date, and the issue of the Contractor's statement (clause 4.22.1). The Final Payment Notice shows the difference between the Final Sub-Contract Sum and the interim payments made (clause 4.22.2).

Like the Final Certificate, the Final Payment Notice is conclusive evidence on the matters in clause 1.8.1, unless either party starts proceedings before or within 10 days after receiving it (clause 1.8.2.1), or in the other cases clause 1.8.2 lists. Ten days is short. Read the Final Payment Notice the day it arrives.

What to put in the final account

Build it from the contract sum, not from the last valuation. Show each variation with its valuation and the basis, each provisional sum adjusted, any loss and expense, and the deductions. Keep it in the order of the contract documents so that it can be checked line by line, and send the supporting documents with it.

Disputed items do not hold up the agreed ones. List them separately with the grounds, so that the rest can be agreed and paid. Our guide on valuing variations under JCT explains the rules for the variations.

A worked example

Invented example

Practical completion
Fri 30 Apr 2027
Documents due by
Wed 30 Jun 2027
Statement sent and received
Fri 10 Dec 2027
Dispute in writing by
Mon 10 Jan 2028

A Sub-Contractor on the JCT Design and Build Sub-Contract 2016 reaches practical completion of its works on Friday 30 April 2027. It must send the documents for the final account not later than 2 months later, by Wednesday 30 June 2027, and it sends them on Monday 14 June 2027.

The Contractor's statement of the Final Sub-Contract Sum is sent and received on Friday 10 December 2027, well within its 8 months. The Sub-Contractor disagrees with two variation valuations. It must dispute them in writing, giving grounds, within one month, by Monday 10 January 2028. If it was sent earlier than it arrived, count the month from the day it was sent. If it does not, the Final Sub-Contract Sum is deemed to take account of all adjustments, including those two.

Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.

Questions

Common questions

How long does a Sub-Contractor have to dispute the final account statement under JCT?
Under clause 4.21.4 of the JCT Design and Build Sub-Contract 2016, one month from the submission of the Contractor's statement. If nothing in it is disputed in writing, with grounds, in that time, the Final Sub-Contract Sum is deemed to take account of all adjustments.
Is the Final Certificate conclusive?
Under clause 1.9 of the Standard Building Contract 2016 it is conclusive evidence on the matters listed there, including that all adjustments to the Contract Sum have been made, unless proceedings are started before or within 28 days after its issue.
What about the Sub-Contractor's Final Payment Notice?
Under clause 1.8 of the sub-contract the Final Payment Notice is conclusive evidence on similar matters, unless either party starts proceedings before or within 10 days after receiving it, or in the other cases clause 1.8.2 lists.

Preparing the final account

Puncheur's final account page explains what the statement contains and how the periods are taken from your own contract.

See the Final account statement

Sources

  1. JCT Standard Building Contract Without Quantities 2016, clauses 1.9, 4.25 and 4.26. jctltd.co.uk. Checked 20 November 2026.
  2. JCT Design and Build Sub-Contract Conditions 2016, clauses 1.8, 4.21 and 4.22. jctltd.co.uk. Checked 20 November 2026.

A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.