Under JCT half the retention is released at practical completion and the rest after making good. Sub-contracts and NEC4 Option X16 set their own release points.

Published
20 November 2026
For
Main Contractors and Sub-Contractors
Law checked
20 November 2026
Reading time
5 minutes
On this page
  1. What retention is for
  2. Under a JCT main contract
  3. Under a JCT sub-contract
  4. Bespoke sub-contracts and the Construction Act
  5. Under NEC4
  6. A worked example
  7. Common questions

Under a JCT Standard Building Contract, retention is released in two halves. Once the works reach practical completion, only half the Retention Percentage may be held, so the first half is released in the next Interim Certificate. Once the Certificate of Making Good is issued at the end of the Rectification Period, no retention may be held, so the rest is released. JCT sub-contracts, NEC4 and bespoke forms each set their own release points, and the Construction Act limits how a sub-contract can tie release to the main contract.

This article describes the JCT Standard Building Contract 2016, the JCT Design and Build Sub-Contract 2016 and the NEC4 Engineering and Construction Contract, June 2017 edition with amendments October 2020. If your contract is on a later edition or is amended, check the clause numbers in your own copy.

What retention is for

Retention is a percentage held back from each interim payment as security for defects. It protects the party paying against work that turns out not to be in accordance with the contract. For the party being paid it is money already earned, and on a long job with a 3% or 5% rate it can add up to a large sum.

Because it is held back from payments, the rules on when it comes back are part of the payment terms. A Main Contractor holds retention from its Sub-Contractors while the Employer holds retention from the Main Contractor, and the two release dates are not always the same.

Under a JCT main contract

Clause 4.19 of the Standard Building Contract 2016 sets the amounts. The Retention Percentage stated in the Contract Particulars may be deducted while the works have not reached practical completion. Once they have, only half the Retention Percentage may be deducted until the Certificate of Making Good is issued. The same applies section by section where the works are in Sections, and to any part the Employer has taken into possession early.

The Certificate of Making Good is issued under clause 2.39 when the Architect/Contract Administrator is satisfied that the defects it required to be made good under clause 2.38 have been made good. Under clause 2.38 the schedule of defects is delivered not later than 14 days after the Rectification Period expires. Once the certificate is issued, clause 4.19 no longer allows any retention to be deducted, so the balance comes back.

With each Interim Certificate, clause 4.17.2 requires a statement of the retention deducted and of any amount being released. Clause 4.17.1 says the Employer holds the retention as trustee for the Contractor, and under clause 4.17.3 a Contractor can ask for it to be placed in a separate bank account, unless the Employer is a Local or Public Authority.

Under a JCT sub-contract

The JCT Design and Build Sub-Contract 2016 works differently. Under clause 4.12, half the stated percentage may be deducted once the Sub-Contract Works reach practical completion. The balance is not tied to the main contract. It is included in the next interim payment after the Retention Release Date stated in the Sub-Contract Particulars, provided the Sub-Contract Works as a whole have reached practical completion and no defects are apparent at that date.

If defects are apparent, the balance is paid in the payment after they are made good. Any apparent defects not already notified must be listed and notified to the Sub-Contractor within 14 days after the Retention Release Date. If the total retention would be below the Minimum Retention Amount in the Sub-Contract Particulars, none is deducted at all.

Bespoke sub-contracts and the Construction Act

Many bespoke sub-contracts say the second half of retention is released only when the main contract Certificate of Making Good is issued. That makes the Sub-Contractor wait for work it does not control, sometimes years after its own work finished.

Section 110(1A) of the Construction Act addresses this. It opens as follows.

Housing Grants, Construction and Regeneration Act 1996, section 110(1A)
"The requirement in subsection (1)(a) to provide an adequate mechanism for determining what payments become due under the contract, or when, is not satisfied where a construction contract makes payment conditional on"

It then lists two cases, "the performance of obligations under another contract" and "a decision by any person as to whether obligations under another contract have been performed". Where a contract does not provide an adequate mechanism, section 110(3) applies the relevant provisions of the Scheme for Construction Contracts instead. A retention clause that depends on the main contract certificate is therefore open to challenge. Section 110(1C) disapplies this where the contract is for construction operations to be carried out by another person and the obligations are that person's obligations to carry them out. That exception is not aimed at an ordinary sub-contract retention clause, but take advice on your own clause before relying on this point.

Under NEC4

Retention under NEC4 is Option X16. Once the Price for Work Done to Date passes the retention free amount in the Contract Data, the retention percentage is applied to the excess. The amount retained is halved in the next assessment after Completion of the whole of the works, or after the Client takes over the whole of the works if that is earlier. It then stays at that level until the date the Defects Certificate is due, and nothing is retained in assessments after that date.

Option X16 also allows a retention bond, if the Contract Data allows it or the Client agrees. Once the bond is given, any amount already retained is paid to the Contractor in the next assessment.

A worked example

Invented example

Gross valuation
£400,000
Retention Percentage
3%
Released at completion
£6,000
Released after making good
£6,000

On a Standard Building Contract 2016, the Retention Percentage is 3%. At practical completion the gross valuation of the work is £400,000, so £12,000 has been retained.

Once practical completion is certified, only half the Retention Percentage may be held, so retention falls to £6,000 and £6,000 is released in the next Interim Certificate. The remaining £6,000 is released once the Certificate of Making Good is issued after the Rectification Period.

ItemBasis the notice statesSum
Retention before completion3% of the gross valuation of £400,000£12,000
Released after practical completionRetention falls to half the Retention Percentage£6,000
Released after making goodNo Retention once the Certificate of Making Good is issued£6,000

Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.

Questions

Common questions

When is the first half of retention released under JCT?
Under clause 4.19 of the Standard Building Contract 2016, once the works reach practical completion only half the Retention Percentage may be deducted, so the other half comes back in the next Interim Certificate.
Can a Sub-Contractor's retention be held until the main contract is finished?
Section 110(1A) of the Construction Act says a payment mechanism is not adequate where it makes payment conditional on the performance of obligations under another contract, or on a decision as to whether they have been performed. A sub-contract clause that waits for the main contract's Certificate of Making Good is open to challenge on that ground.
Does retention have to be held in a separate account?
Under clause 4.17 of the Standard Building Contract 2016, the Employer holds retention as trustee for the Contractor and, unless it is a Local or Public Authority, must place it in a separate bank account if the Contractor asks.

Asking for the release

Puncheur's retention release page explains what the request contains and how the release dates are taken from your own contract.

See the Request for release of retention

Sources

  1. Housing Grants, Construction and Regeneration Act 1996, section 110. legislation.gov.uk. Checked 20 November 2026.
  2. JCT Standard Building Contract Without Quantities 2016, clauses 2.38, 2.39, 4.17 and 4.19. jctltd.co.uk. Checked 20 November 2026.
  3. JCT Design and Build Sub-Contract Conditions 2016, clause 4.12. jctltd.co.uk. Checked 20 November 2026.
  4. NEC4 Engineering and Construction Contract, June 2017 with amendments October 2020, Option X16. neccontract.com. Checked 20 November 2026.

A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.