How are variations valued under JCT?

Under JCT a variation is valued at the contract rates for similar work, with a fair allowance for changed conditions, or at fair rates if it is not similar.

Published
20 November 2026
For
Main Contractors and Sub-Contractors
Law checked
20 November 2026
Reading time
5 minutes
On this page
  1. What counts as a variation
  2. Who values it
  3. The valuation rules
  4. Daywork
  5. Variation Quotations
  6. Delay is claimed separately
  7. A worked example
  8. Common questions

Under a JCT contract a variation is valued in one of three ways, unless the parties agree a price. Where the work is of similar character to work in the contract documents and done under similar conditions, the contract rates and prices apply. Where it is similar work but the conditions or quantity have changed, the contract rates are the starting point with a fair allowance for the difference. Where it is not similar work, it is valued at fair rates and prices. Daywork is the fallback for work that cannot be measured.

This article describes the JCT Standard Building Contract Without Quantities 2016 and the JCT Design and Build Sub-Contract 2016. Many contracts are amended, so check the valuation clauses in your own copy.

What counts as a variation

Clause 5.1 of the Standard Building Contract defines a Variation widely. It covers the alteration or modification of the design, quality or quantity of the Works, including adding, omitting or substituting work, changing the kind or standard of materials, and removing work from site. It also covers obligations or restrictions imposed by the Employer on access, working space, working hours and the order of the work.

The sub-contract follows the same pattern for directions from the Main Contractor. Instructions given on site should be confirmed in writing before the work is done. Our guide on confirming a verbal instruction explains how.

Who values it

Under clause 5.2.1 of the Standard Building Contract, the value of a Variation is the amount agreed by the Employer and the Contractor or, where not agreed, the amount valued by the Quantity Surveyor, which the contract calls a Valuation.

Under clause 5.2 of the sub-contract, unless the Contractor and the Sub-Contractor agree otherwise, the Valuation is made by the Contractor. So a Sub-Contractor's variation is valued by the Main Contractor it is working for, under the rules in clauses 5.6 to 5.12.

The valuation rules

The sub-contract sets out the three cases most plainly, in clause 5.6.1 for work valued on the Adjustment Basis.

  • Where the work is of similar character to, is executed under similar conditions as, and does not significantly change the quantity of, work set out in the sub-contract documents, the rates and prices for that work determine the valuation.
  • Where it is of similar character but is not executed under similar conditions or significantly changes the quantity, those rates and prices are the basis, and the Valuation includes a fair allowance for the difference.
  • Where it is not of similar character, it is valued at fair rates and prices.

Clause 5.6.1 of the Standard Building Contract makes the same distinction in two limbs, with the fair allowance for changed conditions or quantity built into the first. Omitted work is valued at the contract rates under clause 5.6.2 of the main contract and clause 5.6.2 of the sub-contract.

Preliminaries can move too. Where appropriate, an allowance is made for any addition to or reduction of preliminary items (main contract clause 5.6.3, sub-contract clause 5.8.3). And under main contract clause 5.9 and sub-contract clause 5.11, if a variation substantially changes the conditions under which other work is done, that other work is treated as a Variation as well.

Daywork

Where work cannot be valued by measurement, it is valued as daywork. That is the prime cost of the work, calculated under the RICS definition current at the base date, with the percentage additions stated in the contract, or at a schedule of daywork rates where the sub-contract includes one.

The vouchers matter. They must state the time spent each day, the workers' names, the plant and the materials, and reach the Contractor for verification not later than 5 Business Days after the work is done under the sub-contract (clause 5.9), or the Architect/Contract Administrator not later than 7 Business Days under the main contract (clause 5.7). Late vouchers give the other side an argument against paying for the work.

Variation Quotations

The contract can ask for a price before the work is done. Where the instruction or direction says a Variation Quotation is to be provided under Schedule 2, the quotation is given in that form, unless the Contractor or Sub-Contractor notifies within 7 days (main contract clause 5.3.1) or 4 days (sub-contract clause 5.3.1) that it disagrees with the procedure being used. An accepted quotation fixes the price, and a later change to that work is valued fairly having regard to it, and that valuation includes any direct loss and expense the change causes.

Delay is claimed separately

The valuation of a variation does not include its effect on progress. Clause 5.10.2 of the main contract and clause 5.12.2 of the sub-contract say no allowance is made under the valuation rules for any effect on regular progress, or for loss and expense reimbursed under another provision. If a variation delays or disrupts the work, give notice and claim it as loss and expense. Our guide on JCT loss and expense explains how.

A worked example

Invented example

Bill rate
£52.00 a m²
Valued at bill rate
£7,800.00
With fair allowance
£2,329.60
Daywork vouchers due
Mon 15 Mar 2027

A Sub-Contractor on the JCT Design and Build Sub-Contract 2016, on the Adjustment Basis, has blockwork in its bills at £52.00 a m². The Contractor directs an additional 150 m² of the same blockwork on the ground floor, under the same conditions. That is similar work under similar conditions, so it is valued at the bill rate, £7,800.00.

The direction also adds 40 m² of the same blockwork at roof level, built from a scaffold that the original work did not need. The work is similar but the conditions are not, so the bill rate is the basis with a fair allowance. The parties agree 12% for the scaffold working, giving £2,329.60. The Valuation of the Variation is £10,129.60.

Removing an old wall to make way for it cannot be measured, so it is done on daywork on Monday 8 March 2027. The vouchers must reach the Contractor not later than 5 Business Days later, by Monday 15 March 2027.

ItemBasis the notice statesSum
Similar work, similar conditions150 m² at the bill rate of £52.00 (clause 5.6.1.1)£7,800.00
Similar work, changed conditions40 m² at £52.00 plus an agreed allowance of 12% for working from the scaffold (clause 5.6.1.2)£2,329.60
Valuation of the VariationBefore any daywork£10,129.60

Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.

Questions

Common questions

Who values a variation under a JCT contract?
Under the Standard Building Contract 2016 the value is the amount agreed by the Employer and the Contractor or, where not agreed, the amount valued by the Quantity Surveyor. Under the JCT Design and Build Sub-Contract 2016, unless otherwise agreed, the Contractor values it.
When does daywork apply?
Only where the work cannot be valued by measurement under the valuation rules. Under the sub-contract the daywork vouchers must reach the Contractor not later than 5 Business Days after the work is done, and under the main contract not later than 7 Business Days.
Does the valuation of a variation include delay costs?
Not as a rule. Both forms say no allowance is made under the valuation rules for any effect on regular progress, or for direct loss and/or expense that would be reimbursed under another provision. That is claimed as loss and expense. The exception is a change to work priced by an accepted Variation Quotation, whose valuation includes that loss and expense (clause 5.3.3 of both forms).

Pricing the variation

Puncheur's variation quotation page explains what the quotation contains and how it follows the valuation rules in your own contract.

See the Variation quotation and variations register

Sources

  1. JCT Standard Building Contract Without Quantities 2016, clauses 5.1 to 5.10. jctltd.co.uk. Checked 20 November 2026.
  2. JCT Design and Build Sub-Contract Conditions 2016, clauses 5.2 to 5.12. jctltd.co.uk. Checked 20 November 2026.

A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.