How to confirm a verbal instruction
A verbal instruction under JCT has no immediate effect. Confirm it in writing within 7 days. Under NEC4 an instruction must be in a form that can be recorded.
On this page
A verbal instruction should be confirmed in writing straight away. Under a JCT Standard Building Contract, an instruction from the Architect/Contract Administrator that is not in writing has no immediate effect. The Contractor confirms its terms in writing within 7 days, and if the Architect/Contract Administrator does not dissent within 7 days of receiving that confirmation, the instruction takes effect. Under NEC4, an instruction must be in a form that can be read, copied and recorded, so a spoken instruction needs to be put in writing before it is relied on.
This article describes the JCT Standard Building Contract 2016, the JCT Design and Build Sub-Contract 2016 and the NEC4 Engineering and Construction Contract, June 2017 edition with amendments October 2020. If your contract is on a later JCT edition or is amended, check the clause numbers and periods in your own copy.
Why it matters
Instructions change the work, and changed work is paid for as a Variation or a compensation event. A Main Contractor or Sub-Contractor that acts on an instruction it cannot prove may find the instruction denied when the account is settled. An Employer or Main Contractor that gives instructions on site without a record may find it harder to control what is being built and what it costs.
A written confirmation fixes three things. Who gave the instruction, what it said, and when.
Under a JCT main contract
Clause 3.12 of the Standard Building Contract 2016 sets out the process. Where the Architect/Contract Administrator gives an instruction otherwise than in writing, it is "of no immediate effect". The Contractor confirms its terms in writing to the Architect/Contract Administrator within 7 days. If the Architect/Contract Administrator does not dissent by notice within 7 days from receipt of that confirmation, the instruction takes effect from the end of that second 7 day period.
Two other routes are available. If the Architect/Contract Administrator confirms the instruction in writing first, or within 7 days of receiving the Contractor's confirmation, it takes effect from the date and in the terms of the Architect/Contract Administrator's own confirmation (clause 3.12.2). And if neither side confirms it but the Contractor does the work anyway, the Architect/Contract Administrator may confirm it with retrospective effect at any time before the Final Certificate (clause 3.12.3).
Clause 1.5 applies to these periods. A period of days after or from a date begins on the following day, and any Public Holiday that falls in it is left out.
Under a JCT sub-contract
The JCT Design and Build Sub-Contract 2016 uses the same structure for directions from the Main Contractor. Under clause 3.7, a direction given otherwise than in writing has no immediate effect. The Sub-Contractor confirms its terms in writing to the Contractor within 7 days, and it takes effect when the Contractor's 7 days to dissent from receipt of the confirmation have expired.
As with the main contract, the Contractor's own written confirmation takes effect from its date and terms, and a direction that neither party confirmed but that the Sub-Contractor complied with may be confirmed later with retrospective effect.
A Sub-Contractor usually receives instructions from the Main Contractor's site team rather than from the Architect/Contract Administrator. The sub-contract process applies to those directions, whatever the main contract says about the Architect/Contract Administrator's instructions.
Under NEC4
NEC4 takes a different approach. Clause 13.1 requires each communication which the contract requires, including an instruction, to be communicated in a form which can be read, copied and recorded. Clause 13.2 says when a communication has effect, either when it is communicated through the communication system specified in the Scope, or, if none is specified, when it is received at the recipient's notified address.
So there is no deemed confirmation process for a spoken instruction. If the Project Manager tells the Contractor on site to change something, the safe course is to ask the Project Manager to issue it through the communication system, or for the Contractor to record it in a communication and ask the Project Manager to confirm it.
An instruction from the Project Manager that changes the Scope is a compensation event under clause 60.1(1). If the Project Manager has not notified the compensation event, the Contractor notifies it under clause 61.3, and the 8 week time bar in that clause applies. Our guide on notifying a compensation event under NEC covers that step.
What the confirmation should say
Keep it short and factual. Say who gave the instruction, when and where, what was instructed, and which drawing or part of the works it affects. Quote the clause you are confirming under. If you think the instruction is a Variation or a compensation event, or that it will affect time or cost, say so.
Clause 3.13 of the Standard Building Contract 2016 allows the Contractor to ask which provision of the conditions empowers an instruction. If there is any doubt about the power to give it, ask at the same time.
Send it by the method the contract requires and keep proof of when it was received. The receipt date starts the other side's 7 days.
Common mistakes
Waiting until the end of the job. The confirmation is easiest to give, and hardest to dispute, on the day the instruction is given.
Treating a site meeting note as the confirmation. Minutes are often issued late, are rarely sent as a confirmation under the clause, and may be disputed. Send a separate communication.
Assuming the other side will confirm. The retrospective confirmation in clause 3.12.3 is something the Architect/Contract Administrator may do, not something it must do.
A worked example
Invented example
- Instruction given
- Tue 2 Mar 2027
- Last day to confirm
- Tue 9 Mar 2027
- Confirmation received
- Wed 3 Mar 2027
- Takes effect after
- Wed 10 Mar 2027
On a Standard Building Contract 2016, the Architect/Contract Administrator tells the Contractor on site on Tuesday 2 March 2027 to change the floor finish in the entrance hall. The Contractor has until Tuesday 9 March 2027 to confirm it in writing. It sends its confirmation the next morning, by email, received on Wednesday 3 March 2027, and asks for the change to be treated as a Variation.
The Architect/Contract Administrator then has until Wednesday 10 March 2027 to dissent. It does not, so the instruction takes effect when that period expires at the end of Wednesday 10 March 2027. No Public Holiday falls in either period.
Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.
Questions
Common questions
- Is a verbal instruction valid under a JCT contract?
- It can become valid, but not straight away. Clause 3.12.1 of the Standard Building Contract 2016 says an instruction given otherwise than in writing is of no immediate effect until it is confirmed in writing in the way the clause sets out.
- What if nobody confirms the instruction and the work is done anyway?
- Under clause 3.12.3 the Architect/Contract Administrator may confirm it with retrospective effect at any time before the Final Certificate. That is a power, not a duty, so relying on it is a risk for the party that did the work.
- Does NEC4 allow verbal instructions?
- Clause 13.1 requires each communication which the contract requires, including an instruction, to be communicated in a form which can be read, copied and recorded. A spoken instruction should therefore be put in writing through the communication system the Scope sets out before the work is done.
- Does an email count as writing?
- Usually, but check the notices clause first. JCT clause 1.7 and NEC4 clause 13.2 deal with how communications are given, and many contracts are amended to require a particular method.
Confirming it in writing
Puncheur's confirmation of instruction page explains what the confirmation contains and how the periods are taken from your own contract.
See the Confirmation of instructionSources
- JCT Standard Building Contract Without Quantities 2016, clauses 1.5, 3.12 and 3.13. jctltd.co.uk. Checked 20 November 2026.
- JCT Design and Build Sub-Contract Conditions 2016, clauses 1.5 and 3.7. jctltd.co.uk. Checked 20 November 2026.
- NEC4 Engineering and Construction Contract, June 2017 with amendments October 2020, clauses 13.1, 13.2, 14.3, 60.1(1) and 61.3. neccontract.com. Checked 20 November 2026.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.