Checking a construction contract before you sign
Before signing a construction contract, check the payment dates, notice periods and time bars, retention, delay damages and how notices must be served.
On this page
Most commercial disputes start with terms that were not read before signing. Before you sign a construction contract or sub-contract, check how and when you are paid, what notices you must give and by when, what happens if you miss them, how retention comes back, what you pay if you finish late, and how notices must be served. Some terms are fixed by the Construction Act whatever the contract says. Others are only as good as what you agree.
This article applies to Main Contractors signing a main contract and Sub-Contractors signing a sub-contract on JCT, NEC and bespoke terms in England and Wales. It is a checklist, not advice on any particular contract.
Payment
Find the due date, the final date for payment, and the periods for the Payment Notice and the Pay Less Notice. Section 110(1) requires an adequate mechanism for what becomes due and when, and a final date for payment, but leaves the length of the period between the due date and the final date to the parties. So a long period is lawful, and it is a point to negotiate before signing, not after.
But where the contract gives no substantial remedy for late payment, the Late Payment of Commercial Debts (Interest) Act 1998 can start statutory interest 60 days after the later of the work being done and the payer having notice of the sum, unless the agreed date is not grossly unfair to the supplier (section 4(2E) and (2F)).
If the contract does not provide an adequate mechanism, section 110(3) applies the relevant provisions of the Scheme for Construction Contracts instead. The same applies to the notice provisions under section 110A(5). Our guides on the final date for payment and Pay Less Notices explain how the dates work.
Payment tied to someone else
Look for any term that makes payment depend on the Main Contractor or Employer being paid, or on work under another contract being certified. Section 113(1) makes a provision conditional on the payer being paid by a third person ineffective, unless that third person, or another person further up the chain, is insolvent. Section 110(1A) says a payment mechanism is not adequate where payment is conditional on the performance of obligations under another contract, subject to an exception in section 110(1C). Take advice on any clause of this kind.
Notices and time bars
List every notice the contract requires you to give, the period for each and what happens if you miss it. A requirement to notify a delay forthwith, as in clause 2.17.1 of the JCT Design and Build Sub-Contract 2016, is demanding but has no fixed cut off, so treat it as the same day or the next working day. A bespoke clause that says no extension or payment is due unless notice is given within a fixed number of days is a time bar, and you need a system that meets it.
Check how notices must be served. Clause 1.7.4 of the JCT sub-contract requires some notices to be delivered by hand or sent by Recorded Signed For or Special Delivery post. Email may not be enough, and the method is part of a valid notice.
Retention
Note the retention percentage, any limit, and the release dates. A release date that depends on the main contract's certificate of making good can leave a Sub-Contractor waiting years after its own work finished. Our guide on when retention is released explains the Construction Act point.
Late completion
Find the rate of liquidated damages, any cap, and whether the contract has liquidated damages at all. Under clause 2.21 of the JCT Design and Build Sub-Contract the Sub-Contractor is liable for the Main Contractor's direct loss and/or expense instead, if the Main Contractor gives notice within a reasonable time of the expiry of the period for completion, which can include damages the Employer deducts under the main contract. An uncapped liability for someone else's damages is a real risk to price.
Obligations from another contract
A sub-contract can bind you to obligations in the main contract. Clause 2.5.1 of the JCT sub-contract does this for the obligations identified in the Main Contract Information Schedule. A bespoke clause that applies the whole main contract can bind you to terms you have never seen. Ask for them before you sign.
What the Act guarantees anyway
Some rights cannot be signed away. A party to a construction contract has the right to refer a dispute to adjudication (section 108(1)), and if the contract's procedure does not comply, the Scheme's adjudication provisions apply (section 108(5)). If a notified sum is not paid by the final date, the payee may suspend performance after at least seven days' notice stating the grounds (section 112).
A worked example
Invented example
- Final date
- 60 days after the due date
- Delay notice
- Within 7 days
- Retention release
- Employer's certificate
- Notices by
- Recorded delivery
A groundworks Sub-Contractor is offered a bespoke sub-contract. A review against this checklist picks out four terms. The final date for payment is 60 days after the due date. A notice of delay must be given within 7 days of the start of the delay, or no extension or payment is due. Retention is released only when the Employer's certificate of making good is issued under the main contract. And every notice must be sent by recorded delivery, so an email notice would not count.
The 60 day final date is allowed by the Construction Act, so it is a commercial point to negotiate. If the sub-contract has no adequate interest clause for late payment, the Late Payment Act may also start statutory interest before that final date. The 7 day time bar needs a system that gives notice within the week, or a longer period. The retention release term is open to challenge under section 110(1A), subject to the exception in section 110(1C). The recorded delivery requirement goes into the notice procedure for the job. All four are cheaper to deal with before signing than after.
Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.
Questions
Common questions
- Can a construction contract take away the right to adjudicate?
- No. Section 108 of the Construction Act gives a party to a construction contract the right to refer a dispute to adjudication. If the contract does not comply with section 108, the adjudication provisions of the Scheme for Construction Contracts apply.
- What if the payment terms do not comply with the Construction Act?
- To the extent the contract does not provide an adequate payment mechanism and a final date for payment, the relevant provisions of the Scheme for Construction Contracts apply (section 110(3)). The same applies to the payment notice provisions under section 110A(5).
- Is there a maximum final date for payment?
- No. Section 110(1) of the Construction Act leaves the length of the period between the due date and the final date for payment to the parties, so a long period is a commercial point to negotiate. But where the contract gives no substantial remedy for late payment, the Late Payment of Commercial Debts (Interest) Act 1998 can start statutory interest 60 days after the later of the work being done and the payer having notice of the sum, unless the agreed date is not grossly unfair to the supplier.
Reviewing the contract
Puncheur's contract review page explains what the review covers and how it sets out the risks and deadlines in your own contract.
See the documentSources
- Housing Grants, Construction and Regeneration Act 1996, sections 108, 110, 110A, 111, 112 and 113. legislation.gov.uk. Checked 20 November 2026.
- Late Payment of Commercial Debts (Interest) Act 1998, section 4. legislation.gov.uk. Checked 20 November 2026.
- JCT Design and Build Sub-Contract Conditions 2016, clauses 1.7, 2.5, 2.17 and 2.21. jctltd.co.uk. Checked 20 November 2026.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.