What are back-to-back sub-contract terms?

Back-to-back terms pass main contract obligations down to a Sub-Contractor. JCT staggers the periods so the Main Contractor can pass claims up in time.

Published
20 November 2026
For
Main Contractors and Sub-Contractors
Law checked
20 November 2026
Reading time
4 minutes
On this page
  1. How the JCT sub-contract links to the main contract
  2. How JCT staggers the periods
  3. What back-to-back cannot do
  4. For Main Contractors
  5. For Sub-Contractors
  6. A worked example
  7. Common questions

Back-to-back terms make a sub-contract mirror the main contract, so that obligations the Main Contractor owes the Employer pass down to the Sub-Contractor, and entitlements the Sub-Contractor has can be passed up. Back-to-back does not mean identical. A well drafted sub-contract gives the Sub-Contractor shorter periods to act, and the Main Contractor longer periods to decide, so that the Main Contractor can deal with the Employer first.

This article describes the JCT Standard Building Contract Without Quantities 2016 and the JCT Design and Build Sub-Contract 2016, which JCT designed to work together. Bespoke sub-contracts vary widely, so check your own.

Under clause 2.5.1 of the JCT Design and Build Sub-Contract 2016, so far as the Main Contractor's obligations under the main contract relate to the sub-contract works, the Sub-Contractor observes and complies with them, and indemnifies the Main Contractor against any breach of them. The obligations are those identified in or by the Main Contract Information Schedule.

That schedule is the link. A Sub-Contractor should see the main contract obligations it is taking on before it signs. A Main Contractor should make sure the schedule actually identifies them.

How JCT staggers the periods

Comparing the two forms shows the pattern.

  • Notice of delay. Both require notice forthwith once a delay becomes reasonably apparent (main contract clause 2.27.1, sub-contract clause 2.17.1).
  • Extension of time decision. The Architect/Contract Administrator decides within 12 weeks of receiving the particulars (clause 2.28.2). The Main Contractor decides a Sub-Contractor's extension within 16 weeks (sub-contract clause 2.18.2).
  • Objecting to a Variation Quotation. 7 days under the main contract (clause 5.3.1), 4 days under the sub-contract (clause 5.3.1).
  • Daywork vouchers. 7 Business Days under the main contract (clause 5.7), 5 Business Days under the sub-contract (clause 5.9).
  • Loss and expense. The Architect/Contract Administrator or Quantity Surveyor ascertains within 28 days of the initial assessment and 14 days of each update (clause 4.21.4). The Main Contractor has 42 days and 28 days under the sub-contract (sub-contract clause 4.15.4).
  • Final account documents. 6 months after practical completion under the main contract (clause 4.25.1), 2 months under the sub-contract (clause 4.21.1).
  • Challenging the final payment. 28 days after the Final Certificate under the main contract (clause 1.9.2), 10 days after receiving the Final Payment Notice under the sub-contract (clause 1.8.2).

The longer decision periods give the Main Contractor time to get its own answer from the Employer. The shorter action periods give it time to pass a Sub-Contractor's notice or claim up the line.

What back-to-back cannot do

The Construction Act limits how far payment can be tied to the main contract. Section 113(1) makes a provision ineffective if it makes payment conditional on the payer receiving payment from a third person, unless that third person, or another person further up the chain, is insolvent. Section 110(1A) also says a payment mechanism is not adequate where it makes payment conditional on the performance of obligations under another contract, subject to an exception in section 110(1C), so take advice on your own clause. Our guide on when retention is released explains how that applies to retention.

So a sub-contract can mirror the main contract's obligations and periods, but it cannot simply make the Sub-Contractor wait until the Main Contractor is paid.

For Main Contractors

Check every notice period in the sub-contract against the main contract. If the Sub-Contractor's period to notify a delay or a claim is the same as yours to the Employer, you may receive it too late to pass on. Make sure the Main Contract Information Schedule identifies the obligations you need the Sub-Contractor to carry, and that the sub-contract periods for completion fit your programme.

For Sub-Contractors

Ask for the main contract terms you are being bound by, with the prices removed if need be. A bespoke clause that simply says the main contract applies as if it were repeated in the sub-contract can bind you to obligations you have never seen. Check that the time bars you are given are realistic for a firm of your size, and that payment is not tied to the Main Contractor being paid.

A worked example

Invented example

Particulars received
Mon 1 Mar 2027
Passed to the Employer
Fri 5 Mar 2027
Main contract decision
Fri 28 May 2027
Sub-contract decision
Mon 21 Jun 2027

A Sub-Contractor on the JCT Design and Build Sub-Contract 2016 is delayed by late information from the design team. It gives notice of delay forthwith, and its particulars reach the Main Contractor on Monday 1 March 2027. The Main Contractor passes them up with its own notice under the main contract, and the Architect/Contract Administrator receives the particulars on Friday 5 March 2027.

The Architect/Contract Administrator must decide within 12 weeks, by Friday 28 May 2027. The Main Contractor must decide the Sub-Contractor's extension within 16 weeks of receiving its particulars, by Monday 21 June 2027. The stagger gives the Main Contractor more than three weeks after the main contract decision to decide the sub-contract extension.

Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.

Questions

Common questions

Does back-to-back mean the sub-contract has the same periods as the main contract?
Not in the JCT forms. Many sub-contract periods are deliberately longer for the Main Contractor to decide, and shorter for the Sub-Contractor to act, so that the Main Contractor can deal with the Employer first.
Is a Sub-Contractor bound by the main contract?
Under clause 2.5.1 of the JCT Design and Build Sub-Contract 2016, the Sub-Contractor observes and complies with the Main Contractor's obligations under the main contract, as identified in the Main Contract Information Schedule, so far as they relate to the sub-contract works.
Can a back-to-back clause make payment depend on the Employer paying?
Generally not. Section 113 of the Construction Act makes a provision conditional on the payer being paid by a third person ineffective, unless that third person, or another person further up the chain, is insolvent.

Setting up the sub-contract

Puncheur's sub-contract order page explains what the order contains and how the periods are set against your main contract.

See the Sub-contract order (back to back)

Sources

  1. JCT Standard Building Contract Without Quantities 2016, clauses 2.27, 2.28, 4.25, 5.3 and 5.7. jctltd.co.uk. Checked 20 November 2026.
  2. JCT Design and Build Sub-Contract Conditions 2016, clauses 2.5, 2.17, 2.18, 4.21, 5.3 and 5.9. jctltd.co.uk. Checked 20 November 2026.
  3. Housing Grants, Construction and Regeneration Act 1996, sections 110 and 113. legislation.gov.uk. Checked 20 November 2026.

A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.