Liquidated damages under JCT and NEC

Under JCT the Employer needs a Non-Completion Certificate and notices to deduct liquidated damages. NEC4 Option X7 sets delay damages at a daily rate.

Published
20 November 2026
For
Main Contractors and Sub-Contractors
Law checked
20 November 2026
Reading time
5 minutes
On this page
  1. Why they are fixed in advance
  2. Under a JCT main contract
  3. Deducting them from a payment
  4. If the Completion Date moves
  5. Under a JCT sub-contract
  6. Under NEC4
  7. A worked example
  8. Common questions

Liquidated damages are a sum fixed in the contract that the Contractor pays, or allows, for each week or day it finishes late. Under a JCT Standard Building Contract, the Employer can recover them only if the Architect/Contract Administrator has issued a Non-Completion Certificate and the Employer has given the notices the contract requires. To deduct them from a payment, it also needs a valid Pay Less Notice. Under NEC4, Option X7 sets delay damages at a rate for each day from the Completion Date until the earliest of Completion, take over or a termination certificate.

This article describes the JCT Standard Building Contract 2016 and 2024 editions, the JCT Design and Build Sub-Contract 2016 and the NEC4 Engineering and Construction Contract, June 2017 edition with amendments October 2020. Many contracts are amended, so check your own clauses.

Why they are fixed in advance

Proving the real cost of late completion is slow and uncertain. Liquidated damages replace that exercise with a rate agreed at the start, usually stated in the Contract Particulars or Contract Data as a sum per week or per day. Neither party then has to prove the actual loss.

For the Contractor, it makes the cost of finishing late known before the work starts. For the Employer, it gives a figure it can recover without proving its loss.

Under a JCT main contract

Under clause 2.31 of the Standard Building Contract 2016, if the Contractor fails to complete the works or a Section by the Completion Date, the Architect/Contract Administrator issues a Non-Completion Certificate. If a later Completion Date is then fixed, that certificate is cancelled and a new one issued where needed.

Clause 2.32.1 then sets two conditions. The Non-Completion Certificate must have been issued, and the Employer must have notified the Contractor, before the date of the Final Certificate, that it may require payment of, or may withhold or deduct, liquidated damages. The 2024 edition ties this notification to the due date for the final payment instead.

If both are met, the Employer may give a further notice under clause 2.32.2, not later than 5 days before the final date for payment of the final payment under clause 4.26. That notice states, for the period between the Completion Date and practical completion, whether the Employer requires the Contractor to pay liquidated damages at the stated rate, or will withhold or deduct them from sums due, or both. A lower rate may be stated.

Deducting them from a payment

A footnote to clause 2.32 of the 2016 edition says that if the Employer intends to withhold or deduct liquidated damages, it must also give the appropriate Pay Less Notice under clause 4.11.5. That reflects the Construction Act.

Housing Grants, Construction and Regeneration Act 1996, section 111(1)
"Subject as follows, where a payment is provided for by a construction contract, the payer must pay the notified sum (to the extent not already paid) on or before the final date for payment."

So an Employer that wants to take damages off an interim or final payment needs its clause 2.32 notices and a Pay Less Notice for that payment, given in time. Our guide on Pay Less Notices covers what that notice must say.

If the Completion Date moves

Under clause 2.32.3, if the Architect/Contract Administrator later fixes a later Completion Date, the Employer pays or repays any liquidated damages recovered, allowed or paid for the period up to that later date. An extension of time granted after damages were deducted therefore brings money back to the Contractor. Our guide on JCT extension of time applications explains how that later date is fixed.

Under a JCT sub-contract

The JCT Design and Build Sub-Contract 2016 does not use liquidated damages. Under clause 2.21, if the Sub-Contractor fails to complete within the period for completion, and the Contractor gives notice to that effect within a reasonable time of the period expiring, the Sub-Contractor pays or allows the Contractor's direct loss and/or expense caused by that failure.

That is unliquidated loss. The Main Contractor has to show what it actually lost because of the Sub-Contractor's delay, which may include damages the Employer has deducted under the main contract. A Sub-Contractor facing a claim of this kind is entitled to see how the figure is built up and how it is linked to its own delay.

Bespoke sub-contracts often add a fixed rate. Read the sub-contract particulars before assuming either way.

Under NEC4

Under Option X7 the Contractor pays delay damages at the rate stated in the Contract Data for each day from the Completion Date until the earliest of Completion, the date the Client takes over the works and the date the Project Manager issues a termination certificate. If the Completion Date is later changed after delay damages have been paid, the Client repays the overpayment with interest. If the Client takes over part of the works early, the damages are reduced in proportion to the benefit of that part.

Option X7 is a secondary option. If it is not chosen, NEC4 has no fixed rate and the Client is left to recover its actual loss.

A worked example

Invented example

Completion Date
Fri 30 Apr 2027
Practical completion
Fri 28 May 2027
Revised Completion Date
Fri 14 May 2027
Damages after extension
£5,000

On a Standard Building Contract 2016, the Completion Date is Friday 30 April 2027 and the rate in the Contract Particulars is £2,500 a week. Practical completion is certified on Friday 28 May 2027, four weeks late. A Non-Completion Certificate was issued, the Employer gave its notices under clause 2.32 and a Pay Less Notice, and £10,000 was deducted.

The Contractor's extension of time application is then decided, and the Architect/Contract Administrator fixes a later Completion Date of Friday 14 May 2027. That cancels the first Non-Completion Certificate. The works were not complete by 14 May either, so the Architect/Contract Administrator issues a further one, and the Employer's earlier notice under clause 2.32.1.2 still stands (clause 2.32.4). Under clause 2.32.3 the Employer repays the damages for the two weeks from 30 April to 14 May 2027, £5,000. Damages of £5,000 remain for the two weeks from 14 May to 28 May 2027.

ItemBasis the notice statesSum
Damages deductedFour weeks from 30 April to 28 May 2027 at £2,500 a week£10,000
Less repaidTwo weeks to the revised Completion Date of 14 May 2027£5,000
Damages retainedTwo weeks from 14 May to 28 May 2027£5,000

Puncheur provides Autonomous Commercial Management for Main Contractors and Sub-Contractors in England and Wales.

Questions

Common questions

Can the Employer deduct liquidated damages without a Pay Less Notice?
Not from a notified sum. Section 111 of the Construction Act requires the payer to pay the notified sum unless a valid Pay Less Notice is given in time, and the Standard Building Contract 2016 says in a footnote to clause 2.32 that the Employer must give the appropriate Pay Less Notice as well as its clause 2.32 notice.
What happens to liquidated damages if an extension of time is granted later?
Under clause 2.32.3 of the Standard Building Contract, the Employer pays or repays the damages for the period up to the later Completion Date. Under NEC4 Option X7, the Client repays the overpayment with interest.
Do JCT sub-contracts have liquidated damages?
The JCT Design and Build Sub-Contract 2016 does not set a rate. Under clause 2.21 the Sub-Contractor pays or allows the Contractor's direct loss and/or expense caused by its failure to complete on time, if the Contractor gives notice within a reasonable time.

Dealing with a damages claim

Puncheur's non-completion damages page explains what the notice contains and how the dates and sums are taken from your own contract.

See the Non-completion and liquidated damages notice

Sources

  1. Housing Grants, Construction and Regeneration Act 1996, section 111. legislation.gov.uk. Checked 20 November 2026.
  2. JCT Standard Building Contract Without Quantities 2016, clauses 2.31, 2.32 and 4.11.5. jctltd.co.uk. Checked 20 November 2026.
  3. JCT Standard Building Contract With Quantities 2024, clause 2.32. jctltd.co.uk. Checked 20 November 2026.
  4. JCT Design and Build Sub-Contract Conditions 2016, clause 2.21. jctltd.co.uk. Checked 20 November 2026.
  5. NEC4 Engineering and Construction Contract, June 2017 with amendments October 2020, Option X7. neccontract.com. Checked 20 November 2026.

A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.