Due dates and final dates

The dates in every payment cycle, and how the days are counted.

What is the due date?

The date a payment becomes due. It is set by the contract. Under the Scheme, it is 7 days after the relevant period ends, or the payee's claim if later (Part II para 4).

What is the final date for payment?

The last day by which the sum due must be paid. It is set by the contract. Where the contract does not set it, the Scheme sets it 17 days after the due date (Part II paragraph 8(2)).

By the final date the notified sum must be paid, or the sum in a valid Pay Less Notice (s.111(1) and (6)).

In what order do the dates fall?

The valuation date (set by the contract; the payee usually applies by then), then the due date, then the Payment Notice (not later than five days after the due date, s.110A), then the last day for a Pay Less Notice, then the final date for payment.

Miss the window and the notified sum must be paid in full by the final date. Puncheur reads your contract, sets the payment and notice dates in your contract and tells you which side of the line you are on.

Do weekends and bank holidays count?

Weekends always count. Where something must be done within a period under the Construction Act or the Scheme, such as the Payment Notice or paying by the final date, Christmas Day, Good Friday and bank holidays are left out (section 116 of the Act). The due date is different: it counts every day, so it can fall on a bank holiday. A deadline can fall on a Saturday or Sunday, and that day is still the deadline: serve earlier if you can.

A contract can set its own rule, and the payment calendar states the rule it used for each date.

This is the law of England and Wales. Scotland and Northern Ireland have their own Schemes, and their periods can differ.

A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.