Payment notices and Pay Less Notices
What each notice is, when it must be given, and what happens when one is late or missing.
What is a Payment Notice?
A notice of the sum the payer considers due at the due date, and the basis on which that sum is calculated.
When it is due: Not later than five days after the payment due date (s.110A(1)). The contract cannot allow longer.
If it is late: A late notice may not count: the sum it states may not become the notified sum.
We are paid: what if the payer gives no Payment Notice?
Your application for payment, if it was made in time, stands as your notice of the sum due (section 110B(4) of the Construction Act).
Otherwise you may give your own notice of the sum you consider due (section 110B(2) of the Construction Act). The final date for payment is then postponed by the number of days after the payer's notice was due that you give yours (section 110B(3)).
We pay: which notices must we give, and by when?
On a contract where you pay, such as a sub-contract you let as Main Contractor, the Payment Notice is usually yours to give (s.110A), whether or not the Sub-Contractor has applied. Most contracts, the JCT sub-contracts among them, make the payer give it. It states the sum you consider due at the due date and the basis on which it is calculated.
Miss it, and the Sub-Contractor's application, if made in time, becomes the notified sum (section 110B(4)). To pay less than the notified sum you must give a valid Pay Less Notice in time (s.111(3)); otherwise the notified sum must be paid by the final date (s.111(1) and (6)).
On Autonomous Commercial Management, set the project as one where you pay: the payment calendar then shows your Payment Notice and Pay Less Notice dates, and Puncheur drafts each notice for you to check and serve.
Payment Notice: what it is and when it is due Pay Less Notice: what it is and when it is due
What is a Pay Less Notice?
A notice of intention to pay less than the notified sum (section 111(3)). It states the sum the payer considers due on the date it is served, and the basis on which that sum is calculated.
When it is due: Not later than the period before the final date for payment that the contract sets; if it sets none, seven days before the final date (Scheme, Part II, paragraph 10).
What if a Pay Less Notice is late, or there is none?
A late Pay Less Notice does not reduce the notified sum, which must then be paid in full (s.111). The notified sum must be paid, or the sum in a valid Pay Less Notice (s.111(1) and (6)).
Puncheur can draft a letter to a payer whose Pay Less Notice is late or invalid. It tests the notice's timing against the payment timetable and its content and author against section 111, and states that the notified sum remains payable by the final date for payment.
How does Puncheur help with notices?
On Autonomous Commercial Management, it reads the payment terms from your contract and sets each cycle's dates in your calendar, with reminders before each one. It drafts the notice when you need it, with every date calculated by the platform, for you to check and serve.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.