Suspending work for non-payment
When a payee may suspend, the notice it must give first, and when suspension may start, from either side.
When may I suspend work for non-payment?
When a sum due is not paid in full by the final date for payment and no effective Pay Less Notice was given. At least seven days before suspending (s.112).
Whether to suspend is for your director. It is a serious step: if you are unsure, ask for specialist help before you act.
What notice must I give?
A notice of intention to suspend performance under section 112, stating the grounds on which you intend to suspend.
Suspension may start only 7 days after the notice is given (s.112): each day later moves the start back a day. No suspension date runs until the notice is served: serve it and record its service.
How does Puncheur help?
It drafts the demand when the final date passes unpaid, and the notice of intention to suspend, with the earliest suspension date calculated by the platform. The law needs no demand first (s.112): on Autonomous Commercial Management the notice of intention to suspend comes to your approver once the final date passes unpaid, or after the demand, as you set in the settings (7 days after the demand is served unless you change it).
We pay: our Sub-Contractor has given notice to suspend. What now?
A notice of intention to suspend under section 112 is a serious step. Check whether the sum was due, whether your Payment Notice and any Pay Less Notice were given in time, and the date the notice says suspension may start.
Paying the sum due in full ends the right to suspend. If you dispute the notice, ask for specialist help before suspension starts.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.