The Scheme for Construction Contracts
When the Scheme fills the gaps in a contract, and the periods it sets.
What is the Scheme?
The Scheme for Construction Contracts (England and Wales) Regulations 1998. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.
This is the law of England and Wales. Scotland and Northern Ireland have their own Schemes, and their periods can differ.
What periods does the Scheme set for payment?
Scheme Part II paragraphs 8, 9 and 10: final date 17 days from the due date; payer's notice not later than 5 days after the due date; Pay Less Notice not later than 7 days before the final date.
Under the Scheme, the due date is 7 days after the relevant period ends, or the payee's claim if later (Part II para 4).
How does Puncheur use the Scheme?
Where your contract does not set a payment period, the payment calendar takes it from the Scheme and says so beside the date, so you can see which dates come from your contract and which from the Scheme.
What is the adjudication timetable?
A notice of adjudication can be given at any time (s.108(2)(a)). The referral follows within 7 days of the notice (s.108(2)(b); Scheme Part I para 7(1)). The decision is due within 28 days of the referral, or up to 14 days more (42 days in all) with the referring party's consent, or longer if both agree (s.108(2)(c) and (d)).
Speak to a specialist before you start adjudication, or as soon as one is started against you. Puncheur does not draft adjudication documents.
A guide, not legal advice. The law described here is that of England and Wales; Scotland and Northern Ireland have their own Schemes and differ. The contract's own terms govern; where it has none that comply with the Construction Act, the Scheme for Construction Contracts applies.